Novarly ParcelRenewable sites

Renewable sitesPen Y Cymoedd

Pen Y Cymoedd

Pen Y Cymoedd is an operational 228 MW onshore wind farm in Neath Port Talbot, generating since 19 May 2017. Planning permission was granted on 18 November 2011, 24 months after submission. Operator of record: Vattenfall (previously Nuon Renewables).

228 MW
Capacity
as recorded in REPD
Operational
Status
since 19 May 2017
Wind Onshore
Technology
Vattenfall (previously Nuon Renewables)
Neath Port Talbot
Authority
Wales

Planning and build timeline

Application submitted19 November 2009
Permission granted18 November 2011
24 months after submission
Operational19 May 2017
66 months after consent

Screening a site of your own?

RedlineUK · £39

Neath Port Talbot approves 70% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pen Y Cymoedd’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Neath Port Talbot’s record on onshore wind

Neath Port Talbot has decided 20 onshore wind schemes and approved 70%, taking a median of 24.6 months. See every onshore wind scheme decision in Neath Port Talbot

Other built sites within 15 km

SiteMWDistance
Battery · Operational
220 km
Wind Onshore · Operational
245.3 km
Wind Onshore · Operational
325.6 km
Wind Onshore · Operational
65.8 km
Solar Photovoltaics · Operational
57.8 km
Wind Onshore · Operational
88.8 km
Wind Onshore · Operational
269.3 km
Landfill Gas · Operational
29.5 km

How big is Pen Y Cymoedd?

Pen Y Cymoedd has a recorded installed capacity of 228 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pen Y Cymoedd?

REPD records the operator as Vattenfall (previously Nuon Renewables). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pen Y Cymoedd approved and built?

The application was submitted on 19 November 2009. Permission was granted on 18 November 2011, 24 months later. The site became operational on 19 May 2017, 66 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4595.