Onshore wind planning in Neath Port Talbot

Neath Port Talbot has decided 20 onshore wind schemes and approved 70% of them, taking a median of 24.6 months to decide. Consented capacity: 429 MW. 3 applications still awaiting a decision.

70%
Approved
14 granted · 6 refused
24.6 mo
Median decision
UK 11.5 mo
429 MW
Consented
85 MW refused
6
Appeals
3 allowed on appeal

How Neath Port Talbot compares

Against the 75 UK authorities with 5+ onshore wind decisions, Neath Port Talbot sits in the 54th percentile for approval rate (2 points above the England average) and the 11th percentile for speed.

Decisions by year

510Approved — 1 (2011)111Approved — 4 (2013)Refused — 2 (2013)613Refused — 1 (2014)114Approved — 3 (2015)315Refused — 2 (2017)217Approved — 1 (2018)118Approved — 1 (2021)121Approved — 1 (2022)122
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Kenfig Industrial Estate, Margam - Wind turbine
Infinite Renewables Group Limited · P2022/0372 · 4 mo to decide
1.5Awaiting Construction2022-09-29
Foel Trawsnant
Pennant Walters Ltd · P2014/0825 · 85.2 mo to decide
35Awaiting Construction2021-11-25
Kenfig Industrial Estate, Margam - Wind turbine
Infinite Renewables Group Limited · P2021/0838
1.5Revised2021-08-28
Melin Court
Muirhall Energy (formerly Infinis) · P2014/0883 · 43 mo to decide
18Awaiting Construction2018-05-16
Land South of Ystalyfera
West Coast Energy · P/2015/0803 · 26.7 mo to decide
12Application Refused2017-12-08
Varteg Hill
Engie · P2015/0859 · 25.2 mo to decide
12Application Refused2017-10-24
Maesgwyn Wind Farm - extension (Phase 2)
Pennant Walters (MAESX) · P2014/0733 · 16.1 mo to decide
7Planning Permission Expired2015-12-17
Maesgwyn Wind Farm - extension
Pennant Walters (MAESX) Limited · P2014/0733 · 16.1 mo to decide
2.5Operational2015-12-17
Mynydd Brombil Wind Farm
REG Windpower · P2012/0638 · 34.3 mo to decide
8Operational2015-07-08
Mynydd Marchywel Wind Farm
Renewable Energy Systems (RES) · P2012/0999 · 14.4 mo to decide
10Appeal Refused2014-02-18
Dulais Valley
Acciona Energy · P2008/0024 · 77.4 mo to decide
13.5Application Refused2013-11-12
Hirfynydd
Wind Ventures (Acciona Energy) · P2008/0024 · 69.8 mo to decide
18Appeal Refused2013-11-12
Longlands Lane
Renewable Energy Systems (RES) · 12/1001 · 12.2 mo to decide
1.5Operational2013-11-06
Llynfi Renewable Energy Park, Land at Mynydd Caerau
John Laing Environmental Assets Group · P2010/1148 · 33.4 mo to decide
24Operational2013-08-27
Llynfi Afan Renewable Energy Park
John Laing Environmental Assets Group · P/10/844/FUL� · 32.1 mo to decide
6Operational2013-07-18
Mynydd Y Gwrhyd Windfarm
Awel Aman Tawe Community Energy · P2010/1225 · 27.3 mo to decide
4.7Operational2013-03-21
Pen Y Cymoedd
Vattenfall (previously Nuon Renewables) · P2009/1053 · 23.9 mo to decide
228Operational2011-11-18
Mynydd Y Gwrhyd Windfarm
Awel Aman Tawe Community Energy · P2007/1413 · 19.5 mo to decide
4.7Revised2009-05-07
Maesgwyn
Pennant Wind Energy Ventures · P/2006/1261 · 31.1 mo to decide
26Operational2009-05-05
Mynydd y Betws
ESB (Cambrian Renewable Energy Ltd / Betws Common Holdings Ltd) · E/10446 · 23.8 mo to decide
34.5Operational2007-06-17
Mynydd Y Gwrhyd Windfarm
Awel Aman Tawe · P2004/1381 · 11.9 mo to decide
12.5Revised2005-09-01
Ffynnon Oer Wind Farm
RWE npower · 02/1322 · 6.7 mo to decide
32Operational2003-05-27
Blaencorrwg Wind Farm
Ecogen · 93/9291 · 3.3 mo to decide
19.3Application Refused1994-11-03

Does Neath Port Talbot approve onshore wind schemes?

Yes — of the 20 onshore wind schemes Neath Port Talbot has decided, 70% were approved (14 granted, 6 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Neath Port Talbot?

The median time from application to decision is 24.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Neath Port Talbot consented?

429 MW has been consented across 14 approved schemes, with 85 MW refused. A further 3 applications awaits a decision.

Other technologies in Neath Port Talbot

Solar in Neath Port TalbotBattery storage in Neath Port Talbot

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.