Renewable sites › Ffynnon Oer Wind Farm
Ffynnon Oer Wind Farm
Ffynnon Oer Wind Farm is operational in Neath Port Talbot with a recorded capacity of 32 MW, and has been generating since 2005-12-01.
Planning and build timeline
| Application submitted | 2002-11-05 |
| Permission granted | 2003-05-27 7 months after submission |
| Operational | 2005-12-01 30 months after consent |
Neath Port Talbot’s record on onshore wind
Neath Port Talbot has decided 20 onshore wind schemes and approved 70%, taking a median of 24.6 months. See every onshore wind scheme decision in Neath Port Talbot →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Llynfi Renewable Energy Park, Land at Mynydd Caerau Wind Onshore · Operational | 24 | 4.3 km |
Llynfi Afan Renewable Energy Park Wind Onshore · Operational | 6 | 4.6 km |
Pen y Cymoedd Energy Storage Battery · Operational | 22 | 5.6 km |
Pen Y Cymoedd Wind Onshore · Operational | 228 | 5.6 km |
Maesgwyn Wind Onshore · Operational | 26 | 6.3 km |
Maesgwyn Wind Farm - extension Wind Onshore · Operational | 2.5 | 6.5 km |
Hendre Fawr Farm Solar Photovoltaics · Operational | 11.6 | 6.9 km |
Maerdy Wind Onshore · Operational | 24 | 7.8 km |
How big is Ffynnon Oer Wind Farm?
Ffynnon Oer Wind Farm has a recorded installed capacity of 32 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ffynnon Oer Wind Farm?
REPD records the operator as RWE npower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ffynnon Oer Wind Farm approved and built?
The application was submitted on 2002-11-05. Permission was granted on 2003-05-27, 7 months later. The site became operational on 2005-12-01, 30 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4677.