Renewable sites › Maesgwyn
Maesgwyn
Maesgwyn is operational in Neath Port Talbot with a recorded capacity of 26 MW, and has been generating since 2011-04-14.
Planning and build timeline
| Application submitted | 2006-10-01 |
| Permission granted | 2009-05-05 31 months after submission |
| Operational | 2011-04-14 23 months after consent |
Neath Port Talbot’s record on onshore wind
Neath Port Talbot has decided 20 onshore wind schemes and approved 70%, taking a median of 24.6 months. See every onshore wind scheme decision in Neath Port Talbot →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Maesgwyn Wind Farm - extension Wind Onshore · Operational | 2.5 | 1.2 km |
Maesgwyn solar farm Solar Photovoltaics · Operational | 7.5 | 4.2 km |
Hendre Fawr Farm Solar Photovoltaics · Operational | 11.6 | 4.7 km |
Ffynnon Oer Wind Farm Wind Onshore · Operational | 32 | 6.3 km |
Bryngolwg Farm, Hirwaun - Solar farm Solar Photovoltaics · Operational | 8.94 | 7.4 km |
Rhigos Road - Solar Farm Solar Photovoltaics · Under Construction | 9.88 | 7.9 km |
Hirwaun Stor Generation - Battery Storage Battery · Operational | 21.76 | 8.2 km |
Enviroparks Hirwaun Generation Site Advanced Conversion Technologies · Operational | 20 | 8.5 km |
How big is Maesgwyn?
Maesgwyn has a recorded installed capacity of 26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Maesgwyn?
REPD records the operator as Pennant Wind Energy Ventures. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Maesgwyn approved and built?
The application was submitted on 2006-10-01. Permission was granted on 2009-05-05, 31 months later. The site became operational on 2011-04-14, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2674.