Pates Hill
Pates Hill is operational in West Lothian with a recorded capacity of 14 MW, and has been generating since 2010-01-20.
Planning and build timeline
| Application submitted | 2005-07-21 |
| Permission granted | 2006-06-01 10 months after submission |
| Operational | 2010-01-20 44 months after consent |
West Lothian’s record on onshore wind
West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Longhill Burn Wind Farm Wind Onshore · Under Construction | 45.6 | 1.1 km |
Pearie Law Wind Farm Wind Onshore · Operational | 19.2 | 3.1 km |
Tormywheel Wind Onshore · Operational | 30.75 | 4 km |
Harburnhead Wind Farm Wind Onshore · Operational | 51.7 | 5 km |
Levenseat Waste Management Facility Advanced Conversion Technologies · Operational | 17 | 5.5 km |
Muirhall Wind Onshore · Operational | 12.3 | 5.7 km |
Levenseat EfW Advanced Conversion Technologies · Operational | 12.5 | 5.9 km |
Muirhall Extension Wind Onshore · Operational | 6.8 | 6.5 km |
How big is Pates Hill?
Pates Hill has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pates Hill?
REPD records the operator as Your Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pates Hill approved and built?
The application was submitted on 2005-07-21. Permission was granted on 2006-06-01, 10 months later. The site became operational on 2010-01-20, 44 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3232.