Renewable sites › Pates Hill
Pates Hill
Pates Hill is an operational 14 MW onshore wind farm in West Lothian, generating since 20 January 2010. Planning permission was granted on 1 June 2006, 10 months after submission. Operator of record: Your Energy.
Planning and build timeline
| Application submitted | 21 July 2005 |
| Permission granted | 1 June 2006 10 months after submission |
| Operational | 20 January 2010 44 months after consent |
Screening a site of your own?
West Lothian approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pates Hill’s recorded coordinate — swap in your own postcode or coordinates.
West Lothian’s record on onshore wind
West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Under Construction | 45.6 | 1.1 km |
Wind Onshore · Operational | 19.2 | 3.1 km |
Wind Onshore · Operational | 30.75 | 4 km |
Wind Onshore · Operational | 51.7 | 5 km |
Advanced Conversion Technologies · Operational | 17 | 5.5 km |
Wind Onshore · Operational | 12.3 | 5.7 km |
Advanced Conversion Technologies · Operational | 12.5 | 5.9 km |
Wind Onshore · Operational | 6.8 | 6.5 km |
How big is Pates Hill?
Pates Hill has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pates Hill?
REPD records the operator as Your Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pates Hill approved and built?
The application was submitted on 21 July 2005. Permission was granted on 1 June 2006, 10 months later. The site became operational on 20 January 2010, 44 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3232.