Renewable sites › Longhill Burn Wind Farm
Longhill Burn Wind Farm
Longhill Burn Wind Farm is under construction in West Lothian with a recorded capacity of 45.6 MW.
Planning and build timeline
| Application submitted | 2019-04-15 |
| Permission granted | 2020-04-17 12 months after submission |
| Operational | not recorded |
West Lothian’s record on onshore wind
West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pates Hill Wind Onshore · Operational | 14 | 1.1 km |
Tormywheel Wind Onshore · Operational | 30.75 | 2.9 km |
Pearie Law Wind Farm Wind Onshore · Operational | 19.2 | 4.2 km |
Levenseat Waste Management Facility Advanced Conversion Technologies · Operational | 17 | 4.4 km |
Levenseat EfW Advanced Conversion Technologies · Operational | 12.5 | 4.9 km |
Muirhall Wind Onshore · Operational | 12.3 | 5.8 km |
Harburnhead Wind Farm Wind Onshore · Operational | 51.7 | 6 km |
Muirhall Extension Wind Onshore · Operational | 6.8 | 6.3 km |
How big is Longhill Burn Wind Farm?
Longhill Burn Wind Farm has a recorded installed capacity of 45.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Longhill Burn Wind Farm?
REPD records the operator as EnergieKontor UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Longhill Burn Wind Farm approved and built?
The application was submitted on 2019-04-15. Permission was granted on 2020-04-17, 12 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6327.