Renewable sitesPearie Law Wind Farm

Pearie Law Wind Farm

Pearie Law Wind Farm is an operational 19.2 MW onshore wind farm in West Lothian, generating since 1 December 2016. Planning permission was granted on 8 July 2014, 27 months after submission. Operator of record: EDF Energy Renewables.

19.2 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 2016
Wind Onshore
Technology
EDF Energy Renewables
West Lothian
Authority
Scotland

Planning and build timeline

Application submitted17 April 2012
Permission granted8 July 2014
27 months after submission
Operational1 December 2016
29 months after consent

Screening a site of your own?

RedlineUK · £39

West Lothian approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pearie Law Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

West Lothian’s record on onshore wind

West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
51.72.3 km
Wind Onshore · Operational
143.1 km
Wind Onshore · Under Construction
45.64.2 km
Wind Onshore · Operational
12.36.1 km
Wind Onshore · Operational
30.757.1 km
Wind Onshore · Operational
6.87.4 km
Wind Onshore · Operational
8.37.4 km
Solar Photovoltaics · Operational
1.38.4 km

How big is Pearie Law Wind Farm?

Pearie Law Wind Farm has a recorded installed capacity of 19.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pearie Law Wind Farm?

REPD records the operator as EDF Energy Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pearie Law Wind Farm approved and built?

The application was submitted on 17 April 2012. Permission was granted on 8 July 2014, 27 months later. The site became operational on 1 December 2016, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4211.