Novarly ParcelRenewable planning

Renewable planning Onshore windWest Lothian

Onshore wind planning in West Lothian

West Lothian has decided 13 onshore wind schemes and approved 85% of them, taking a median of 11.3 months to decide. Consented capacity: 184 MW. 4 applications still awaiting a decision.

85%
Approved
11 granted · 2 refused
11.3 mo
Median decision
UK 11.5 mo
184 MW
Consented
50 MW refused
3
Appeals
2 allowed on appeal

How West Lothian compares

Against the 75 UK authorities with 5+ onshore wind decisions, West Lothian sits in the 85th percentile for approval rate (17 points above the England average) and the 67th percentile for speed.

Decisions by year

35Refused — 1 (2013)113Approved — 1 (2014)114Approved — 1 (2015)115Approved — 1 (2016)116Refused — 1 (2017)117Approved — 2 (2020)220Approved — 2 (2021)221Approved — 1 (2023)123Approved — 1 (2024)124
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
Drumduff Wind Farm Extension
Green Power (International) Limited · 0504/FUL/23 · 10.3 mo to decide
15Awaiting Construction2024-04-25
Heights Road, Blackridge - Woodend Wind Farm
Wind Estate (UK) Ltd · 0434/FUL/23
19.8Application Submitted2023-06-16
Southrigg 3 - Wind Turbine
SR Wind Limited · 23/00286/FUL
4.2Application Submitted2023-03-10
Harburnhead Windfarm - Wind Turbine
Caber Energy Limited · 0907/FUL/22 · 3.4 mo to decide
4Awaiting Construction2023-01-23
Gladsmuir Hills - Wind Farm
Wind Estate (UK) Ltd · 0706/FUL/22
41Application Submitted2022-08-25
Pearie Law 2 - Wind turbines
Wind Estate (UK) Ltd · 0124/FUL/21 · 10.4 mo to decide
14.4Awaiting Construction2021-12-22
Camilty Plantation - Wind Farm
EDF Energy Renewables · 0320/FUL/21 · 5.7 mo to decide
25.8Awaiting Construction2021-10-05
Camilty Wind Farm
EDF Energy Renewables (formerly Partnerships for Renewables/Camilty Wind Farm LLP) · 0219/FUL/13 · 101.4 mo to decide
25.8Revised2021-09-21
Longhill Burn Wind Farm
EnergieKontor UK · 0359/FUL/19� · 12.1 mo to decide
45.6Under Construction2020-04-17
Tormywheel Wind Farm Extension
Muirhall Energy · LIVE/0226/FUL/17 · 35.2 mo to decide
5Awaiting Construction2020-03-06
Fauch Hill
Fauch Hill Sustainable Energy · LIVE/0235/FUL/17 · 8.6 mo to decide
48Appeal Refused2017-12-20
Drumelzie
Muirhall Energy (formerly Infinis) · LIVE/0154/FUL/15 · 20.8 mo to decide
1.5Planning Permission Expired2016-12-02
Drumduff
Green Breeze Energy Ltd · 0138/FUL/14 · 15.7 mo to decide
8.5Operational2015-06-18
Pearie Law Wind Farm
EDF Energy Renewables · 0267/FUL/12 · 26.7 mo to decide
19.2Operational2014-07-08
PATES HILL WIND FARM Extension
Longhill Wind Farm Ltd · 0466/FUL/13
6Application Withdrawn2014-01-31
Cowdenhead Wind Turbines
WhiteRock Energy UK Ltd · 0146/FUL/13 · 6.2 mo to decide
1.5Application Refused2013-09-11
Tormywheel
BlackRock (formerly Muirhall Energy) · 0551/FUL/11 · 28 mo to decide
30.75Operational2007-06-07
Pates Hill
Your Energy · 0653/FUL/07 · 10.3 mo to decide
14Operational2006-06-01

Does West Lothian approve onshore wind schemes?

Yes — of the 13 onshore wind schemes West Lothian has decided, 85% were approved (11 granted, 2 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in West Lothian?

The median time from application to decision is 11.3 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has West Lothian consented?

184 MW has been consented across 11 approved schemes, with 50 MW refused. A further 4 applications awaits a decision.

Other technologies in West Lothian

Solar in West LothianBattery storage in West Lothian

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.