Novarly ParcelRenewable sites

Renewable sitesTormywheel

Tormywheel

Tormywheel is an operational 30.75 MW onshore wind farm in West Lothian, generating since 17 March 2017. Planning permission was granted on 7 June 2007, 28 months after submission. Operator of record: BlackRock (formerly Muirhall Energy).

30.75 MW
Capacity
as recorded in REPD
Operational
Status
since 17 March 2017
Wind Onshore
Technology
BlackRock (formerly Muirhall Energy)
West Lothian
Authority
Scotland

Planning and build timeline

Application submitted4 February 2005
Permission granted7 June 2007
28 months after submission
Operational17 March 2017
117 months after consent

Screening a site of your own?

RedlineUK · £39

West Lothian approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tormywheel’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

West Lothian’s record on onshore wind

West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian

Other built sites within 15 km

SiteMWDistance
Advanced Conversion Technologies · Operational
171.5 km
Advanced Conversion Technologies · Operational
12.52.9 km
Wind Onshore · Under Construction
45.62.9 km
Wind Onshore · Operational
144 km
Wind Onshore · Operational
6.86.6 km
Wind Onshore · Operational
8.36.6 km
Wind Onshore · Operational
27.26.8 km
Wind Onshore · Operational
12.36.9 km

How big is Tormywheel?

Tormywheel has a recorded installed capacity of 30.75 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tormywheel?

REPD records the operator as BlackRock (formerly Muirhall Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tormywheel approved and built?

The application was submitted on 4 February 2005. Permission was granted on 7 June 2007, 28 months later. The site became operational on 17 March 2017, 117 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4263.

Novarly Parcel · official public data, read properly · parcel.novarly.com