Renewable sites › Tormywheel
Tormywheel
Tormywheel is operational in West Lothian with a recorded capacity of 30.75 MW, and has been generating since 2017-03-17.
Planning and build timeline
| Application submitted | 2005-02-04 |
| Permission granted | 2007-06-07 28 months after submission |
| Operational | 2017-03-17 117 months after consent |
West Lothian’s record on onshore wind
West Lothian has decided 13 onshore wind schemes and approved 85%, taking a median of 11.3 months. See every onshore wind scheme decision in West Lothian →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Levenseat Waste Management Facility Advanced Conversion Technologies · Operational | 17 | 1.5 km |
Levenseat EfW Advanced Conversion Technologies · Operational | 12.5 | 2.9 km |
Longhill Burn Wind Farm Wind Onshore · Under Construction | 45.6 | 2.9 km |
Pates Hill Wind Onshore · Operational | 14 | 4 km |
Muirhall South Wind Onshore · Operational | 8.3 | 6.6 km |
Muirhall Extension Wind Onshore · Operational | 6.8 | 6.6 km |
West Benhar wind farm Wind Onshore · Operational | 27.2 | 6.8 km |
Muirhall Wind Onshore · Operational | 12.3 | 6.9 km |
How big is Tormywheel?
Tormywheel has a recorded installed capacity of 30.75 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tormywheel?
REPD records the operator as BlackRock (formerly Muirhall Energy). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tormywheel approved and built?
The application was submitted on 2005-02-04. Permission was granted on 2007-06-07, 28 months later. The site became operational on 2017-03-17, 117 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4263.