Renewable sites › Harburnhead Wind Farm
Harburnhead Wind Farm
Harburnhead Wind Farm is operational in Scottish Government (S36) with a recorded capacity of 51.7 MW, and has been generating since 2016-12-01.
Planning and build timeline
| Application submitted | 2011-12-20 |
| Permission granted | 2014-07-09 31 months after submission |
| Operational | 2016-12-01 29 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pearie Law Wind Farm Wind Onshore · Operational | 19.2 | 2.3 km |
Pates Hill Wind Onshore · Operational | 14 | 5 km |
Muirhall Wind Onshore · Operational | 12.3 | 5.7 km |
Longhill Burn Wind Farm Wind Onshore · Under Construction | 45.6 | 6 km |
Muirhall Extension Wind Onshore · Operational | 6.8 | 7.2 km |
Muirhall South Wind Onshore · Operational | 8.3 | 7.2 km |
Tormywheel Wind Onshore · Operational | 30.75 | 8.8 km |
Levenseat EfW Advanced Conversion Technologies · Operational | 12.5 | 9.7 km |
How big is Harburnhead Wind Farm?
Harburnhead Wind Farm has a recorded installed capacity of 51.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Harburnhead Wind Farm?
REPD records the operator as Gresham House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Harburnhead Wind Farm approved and built?
The application was submitted on 2011-12-20. Permission was granted on 2014-07-09, 31 months later. The site became operational on 2016-12-01, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4225.