Muirhall
Muirhall is operational in South Lanarkshire with a recorded capacity of 12.3 MW, and has been generating since 2011-01-01.
Planning and build timeline
| Application submitted | 2005-03-30 |
| Permission granted | 2008-10-10 42 months after submission |
| Operational | 2011-01-01 27 months after consent |
South Lanarkshire’s record on onshore wind
South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Muirhall Extension Wind Onshore · Operational | 6.8 | 1.6 km |
Muirhall South Wind Onshore · Operational | 8.3 | 1.6 km |
Pates Hill Wind Onshore · Operational | 14 | 5.7 km |
Harburnhead Wind Farm Wind Onshore · Operational | 51.7 | 5.7 km |
Longhill Burn Wind Farm Wind Onshore · Under Construction | 45.6 | 5.8 km |
Levenseat EfW Advanced Conversion Technologies · Operational | 12.5 | 5.9 km |
Pearie Law Wind Farm Wind Onshore · Operational | 19.2 | 6.1 km |
Tormywheel Wind Onshore · Operational | 30.75 | 6.9 km |
How big is Muirhall?
Muirhall has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Muirhall?
REPD records the operator as Lomond Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Muirhall approved and built?
The application was submitted on 2005-03-30. Permission was granted on 2008-10-10, 42 months later. The site became operational on 2011-01-01, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4683.