Muirhall

Muirhall is operational in South Lanarkshire with a recorded capacity of 12.3 MW, and has been generating since 2011-01-01.

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-01-01
Wind Onshore
Technology
Lomond Energy
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted2005-03-30
Permission granted2008-10-10
42 months after submission
Operational2011-01-01
27 months after consent

South Lanarkshire’s record on onshore wind

South Lanarkshire has decided 49 onshore wind schemes and approved 73%, taking a median of 15.9 months. See every onshore wind scheme decision in South Lanarkshire

Other built sites within 15 km

SiteMWDistance
Muirhall Extension
Wind Onshore · Operational
6.81.6 km
Muirhall South
Wind Onshore · Operational
8.31.6 km
Pates Hill
Wind Onshore · Operational
145.7 km
Harburnhead Wind Farm
Wind Onshore · Operational
51.75.7 km
Longhill Burn Wind Farm
Wind Onshore · Under Construction
45.65.8 km
Levenseat EfW
Advanced Conversion Technologies · Operational
12.55.9 km
Pearie Law Wind Farm
Wind Onshore · Operational
19.26.1 km
Tormywheel
Wind Onshore · Operational
30.756.9 km

How big is Muirhall?

Muirhall has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Muirhall?

REPD records the operator as Lomond Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Muirhall approved and built?

The application was submitted on 2005-03-30. Permission was granted on 2008-10-10, 42 months later. The site became operational on 2011-01-01, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4683.