Renewable sitesLevenseat EfW

Levenseat EfW

Levenseat EfW is an operational 12.5 MW advanced conversion plant in South Lanarkshire, generating since 15 December 2017. Planning permission was granted on 1 December 2010, 4 months after submission. Operator of record: Levenseat.

12.5 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2017
Advanced Conversion Technologies
Technology
Levenseat
South Lanarkshire
Authority
Scotland

Planning and build timeline

Application submitted3 August 2010
Permission granted1 December 2010
4 months after submission
Operational15 December 2017
84 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in South Lanarkshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Levenseat EfW’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Advanced Conversion Technologies · Operational
172.6 km
Wind Onshore · Operational
30.752.9 km
Wind Onshore · Under Construction
45.64.9 km
Wind Onshore · Operational
6.85.1 km
Wind Onshore · Operational
8.35.1 km
Wind Onshore · Operational
48.45.6 km
Wind Onshore · Operational
1245.6 km
Wind Onshore · Operational
155.6 km

How big is Levenseat EfW?

Levenseat EfW has a recorded installed capacity of 12.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Levenseat EfW?

REPD records the operator as Levenseat. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Levenseat EfW approved and built?

The application was submitted on 3 August 2010. Permission was granted on 1 December 2010, 4 months later. The site became operational on 15 December 2017, 84 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5200.