Novarly ParcelRenewable sites

Renewable sitesOffice Field

Office Field

Office Field is operational in New Forest with a recorded capacity of 7.2 MW, and has been generating since 2013-03-28.

7.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-28
Solar Photovoltaics
Technology
Anesco
New Forest
Authority
England

Planning and build timeline

Application submitted2012-10-15
Permission granted2012-12-11
2 months after submission
Operational2013-03-28
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

New Forest’s record on solar

New Forest has decided 20 solar farms and approved 75%, taking a median of 2.2 months. See every solar farm decision in New Forest

Other built sites within 15 km

SiteMWDistance
Beckley Solar Farm
Solar Photovoltaics · Operational
1.71.8 km
Double H Nurseries Biomass Plant
Biomass (dedicated) · Operational
1.51.9 km
Efford Landfill (Newmilton)
Landfill Gas · Operational
2.82.5 km
Christchurch Energy
Solar Photovoltaics · Operational
183.3 km
Waterditch Solar Farm
Solar Photovoltaics · Operational
183.4 km
Pennington Recycling Centre
Solar Photovoltaics · Operational
1.210.1 km
Lower Pennington Farm
Solar Photovoltaics · Operational
2.710.8 km
Chapel Lane ERF
EfW Incineration · Under Construction
3.411.2 km

How big is Office Field?

Office Field has a recorded installed capacity of 7.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Office Field?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Office Field approved and built?

The application was submitted on 2012-10-15. Permission was granted on 2012-12-11, 2 months later. The site became operational on 2013-03-28, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1273.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council