Novarly ParcelRenewable planning

Renewable planning SolarNew Forest

Solar planning in New Forest

New Forest has decided 20 solar farms and approved 75% of them, taking a median of 2.2 months to decide. Consented capacity: 67 MW. 2 applications still awaiting a decision.

75%
Approved
15 granted · 5 refused
2.2 mo
Median decision
UK 2.3 mo
67 MW
Consented
24 MW refused
2
Appeals
0 allowed on appeal

How New Forest compares

Against the 298 UK authorities with 5+ solar decisions, New Forest sits in the 4th percentile for approval rate (18 points below the England average) and the 54th percentile for speed.

Decisions by year

35Approved — 1 (2011)111Approved — 3 (2012)312Approved — 2 (2013)213Refused — 1 (2014)114Approved — 1 (2015)Refused — 2 (2015)315Approved — 1 (2016)116Approved — 1 (2021)121Approved — 1 (2022)122Approved — 3 (2023)Refused — 1 (2023)423Approved — 1 (2024)Refused — 1 (2024)224Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (25)

SchemeMWStatusDecided
Staplewood Campus, Marchwood - Solar Panels
Southampton Training Ground · 25/10641 · 1.2 mo to decide
0.2Awaiting Construction2025-08-26
Fletchwood Lane, Totton - Solar Park
Trant Engineering Limited · 25/00760FULL
5.26Application Submitted2025-07-28
Walkford Moor Solar Farm, Walkford Lane - Solar Farm
Boultbee Brooks (Renewables Costock) Limited · 23/11213 · 7.9 mo to decide
15Awaiting Construction2024-08-14
Thornlands Farm, Fletchwood Road - Solar Farm
Enviromena Asset Management UK Limited · 23/01683FULL · 3.6 mo to decide
12Application Refused2024-06-18
Pennington Wastewater Treatment Works, Milford Road - Solar panels
Southern Water · 24/10306
1.28Application Submitted2024-04-15
David Lloyd Leisure Centre, Christchurch Road - Solar PV System
David Lloyd Leisure Limited · 23/10496 · 1.8 mo to decide
0.31Awaiting Construction2023-09-05
Station Mill, Ashford Road - Solar Panels
John Loader Limited · 23/10076 · 1.1 mo to decide
0.22Awaiting Construction2023-03-15
Hoburne Naish, Glenside Naish Estate - Solar panels
Hoburne Naish Holiday Park · 23/10056 · 1.2 mo to decide
0.16Application Refused2023-02-28
Newtown Park House - Energy Centre
Newtown Park House · 22/00767FULL · 3 mo to decide
0.25Awaiting Construction2023-02-22
Morrisons Supermarket, Totton - Solar Photovoltaic System
Morrisons · 22/11034 · 1.4 mo to decide
0.34Awaiting Construction2022-10-17
Hamer Warren Solar Farm
Somerley Estate · 20/11073 · 4.1 mo to decide
23Under Construction2021-02-03
Testwood Water Supply Works
Southern Water Services · 16/11007 · 4.9 mo to decide
1.9Operational2016-12-12
Land South Of Carlton House
West Solent Solar Cooperative · 15/00787 · 1.8 mo to decide
2.2Application Refused2015-12-23
Land South of Bury Road
Lightsource Renewable Energy · 15/11153 · 1.9 mo to decide
4Abandoned2015-09-30
Pennington Recycling Centre
Novus Solar Developments · 15/11012 · 2.7 mo to decide
1.2Operational2015-09-29
Exbury Solar Farm
MTS Exbury Solar · 14/01004 · 2.2 mo to decide
5Appeal Refused2015-02-17
Limolands Farm Solar Array
Locogen · 14/00817 · 2.5 mo to decide
5Appeal Refused2014-12-17
Limolands Farm
Locogen · 14/00470
5Application Withdrawn2014-08-15
Durley Farm
Hive Energy · 14/00361
6.7Application Withdrawn2014-07-04
Lower Pennington Farm
West Solent Solar Cooperative · 13/11100 · 2.9 mo to decide
2.7Operational2013-12-02
The Manor of Cadland Estate - extension
Manor of Cadland · 13/98465 · 2.6 mo to decide
3Operational2013-07-18
Office Field
Anesco · 12/99313 · 1.9 mo to decide
7.2Operational2012-12-11
Beckley Solar Farm
Anesco · 12/98608 · 1.9 mo to decide
1.7Operational2012-06-15
Tavells Lane Solar Farm
Hive Energy · 12/98402 · 1.9 mo to decide
5.3Operational2012-05-08
The Manor of Cadland Estate
The Manor of Cadland Estate · 11/96086 · 3.8 mo to decide
5Operational2011-05-17

Does New Forest approve solar farms?

Yes — of the 20 solar farms New Forest has decided, 75% were approved (15 granted, 5 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in New Forest?

The median time from application to decision is 2.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has New Forest consented?

67 MW has been consented across 15 approved schemes, with 24 MW refused. A further 2 applications awaits a decision.

Other technologies in New Forest

Battery storage in New ForestOnshore wind in New Forest

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report