Novarly ParcelRenewable sites

Renewable sitesChristchurch Energy

Christchurch Energy

Christchurch Energy is an operational 18 MW solar farm in Bournemouth, Christchurch and Poole, generating since 27 March 2015. Planning permission was granted on 29 August 2014, 3 months after submission. Operator of record: New Forest Energy Ltd.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 27 March 2015
Solar Photovoltaics
Technology
New Forest Energy Ltd
Bournemouth, Christchurch and Poole
Authority
England

Planning and build timeline

Application submitted21 May 2014
Permission granted29 August 2014
3 months after submission
Operational27 March 2015
7 months after consent

Screening a site of your own?

RedlineUK · £39

Bournemouth, Christchurch and Poole approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Christchurch Energy’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bournemouth, Christchurch and Poole’s record on solar

Bournemouth, Christchurch and Poole has decided 25 solar farms and approved 88%, taking a median of 2.3 months. See every solar farm decision in Bournemouth, Christchurch and Poole

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
180.4 km
Solar Photovoltaics · Operational
7.23.3 km
Solar Photovoltaics · Operational
1.75 km
Biomass (dedicated) · Operational
1.55.1 km
Landfill Gas · Operational
2.85.8 km
EfW Incineration · Under Construction
3.48.2 km
Biomass (dedicated) · Operational
3.28.3 km
Solar Photovoltaics · Operational
88.4 km

How big is Christchurch Energy?

Christchurch Energy has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Christchurch Energy?

REPD records the operator as New Forest Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Christchurch Energy approved and built?

The application was submitted on 21 May 2014. Permission was granted on 29 August 2014, 3 months later. The site became operational on 27 March 2015, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2308.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode