Renewable sites › Chapel Lane ERF
Chapel Lane ERF
Chapel Lane ERF is under construction in Bournemouth, Christchurch and Poole with a recorded capacity of 3.4 MW.
Planning and build timeline
| Application submitted | 2021-03-02 |
| Permission granted | 2022-12-08 21 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
- Green Belt — Bournemouth, Christchurch and Poole
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eco Composting Biomass (dedicated) · Operational | 3.2 | 0.5 km |
Chapel Lane Parley Solar Farm Phase 1 Solar Photovoltaics · Operational | 20 | 0.6 km |
Chapel Lane Parley Solar Farm Phase 2 Solar Photovoltaics · Operational | 36 | 0.7 km |
Hale Farm Solar Photovoltaics · Operational | 8 | 1.5 km |
Chapel Lane Parley Solar Farm Phase 3 Solar Photovoltaics · Operational | 4 | 1.7 km |
Woodtown Farm Solar Photovoltaics · Operational | 3.8 | 2 km |
Bedborough Farm Solar Photovoltaics · Operational | 7 | 5.9 km |
Homeland Solar Farm Solar Photovoltaics · Operational | 13.2 | 6.4 km |
How big is Chapel Lane ERF?
Chapel Lane ERF has a recorded installed capacity of 3.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chapel Lane ERF?
REPD records the operator as Eco Sustainable Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chapel Lane ERF approved and built?
The application was submitted on 2021-03-02. Permission was granted on 2022-12-08, 21 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8041.