Novarly ParcelRenewable sites

Renewable sitesNewbold Pacey Solar Farm�

Newbold Pacey Solar Farm�

Newbold Pacey Solar Farm� is operational in Stratford-on-Avon with a recorded capacity of 28.7 MW, and has been generating since 2024-11-01.

28.7 MW
Capacity
as recorded in REPD
Operational
Status
since 2024-11-01
Solar Photovoltaics
Technology
Innova Renewables / ISGRenewables
Stratford-on-Avon
Authority
England

Planning and build timeline

Application submitted2022-02-07
Permission granted2022-08-24
7 months after submission
Operational2024-11-01
26 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stratford-on-Avon’s record on solar

Stratford-on-Avon has decided 36 solar farms and approved 94%, taking a median of 3.7 months. See every solar farm decision in Stratford-on-Avon

Other built sites within 15 km

SiteMWDistance
Tollgate Farm
Solar Photovoltaics · Operational
4.33.1 km
Brickyard Barn
Solar Photovoltaics · Operational
4.14.4 km
Banbury Road, Gaydon - Solar Array
Solar Photovoltaics · Operational
186.1 km
Wolseley National Distribution Centre
Solar Photovoltaics · Operational
27.2 km
Land On The East Side Of Fosse Way
Solar Photovoltaics · Operational
107.6 km
The Elms
Solar Photovoltaics · Operational
10.48.4 km
Alscot
Biomass (dedicated) · Operational
1.68.6 km
Ufton
Landfill Gas · Operational
19.4 km

How big is Newbold Pacey Solar Farm�?

Newbold Pacey Solar Farm� has a recorded installed capacity of 28.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Newbold Pacey Solar Farm�?

REPD records the operator as Innova Renewables / ISGRenewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Newbold Pacey Solar Farm� approved and built?

The application was submitted on 2022-02-07. Permission was granted on 2022-08-24, 7 months later. The site became operational on 2024-11-01, 26 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9631.