Novarly ParcelRenewable sites

Renewable sitesAlscot

Alscot

Alscot is operational in Stratford-on-Avon with a recorded capacity of 1.6 MW, and has been generating since 2017-03-03.

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-03
Biomass (dedicated)
Technology
RCMA Stratford
Stratford-on-Avon
Authority
England

Planning and build timeline

Application submitted2013-04-19
Permission grantednot recorded
Operational2017-03-03

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Crimscote Solar Farm and Storage Project
Solar Photovoltaics · Under Construction
49.995.8 km
Crimscote Solar Farm and Storage Project
Battery · Under Construction
5.8 km
Burton Farm
Solar Photovoltaics · Operational
4.45.8 km
Drayton Manor Farm
Solar Photovoltaics · Operational
257.1 km
Newbold Pacey Solar Farm�
Solar Photovoltaics · Operational
28.78.6 km
Blackwell Grange Solar Farm
Solar Photovoltaics · Operational
59.7 km
Norton Hall
Solar Photovoltaics · Operational
2.811.1 km
Tollgate Farm
Solar Photovoltaics · Operational
4.311.4 km

How big is Alscot?

Alscot has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Alscot?

REPD records the operator as RCMA Stratford. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Alscot approved and built?

The application was submitted on 2013-04-19. REPD does not record a grant date. The site became operational on 2017-03-03.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6492.

Novarly Parcel · official public data, read properly · parcel.novarly.com