Banbury Road, Gaydon - Solar Array is operational in Stratford-on-Avon with a recorded capacity of 18 MW, and has been generating since 2025-08-01.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 2025-08-01
Solar Photovoltaics
Technology
Jaguar Land Rover Manufacturing
Stratford-on-Avon
Authority
England

Planning and build timeline

Application submitted2022-11-21
Permission granted2023-03-23
4 months after submission
Operational2025-08-01
28 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stratford-on-Avon’s record on solar

Stratford-on-Avon has decided 36 solar farms and approved 94%, taking a median of 3.7 months. See every solar farm decision in Stratford-on-Avon

Other built sites within 15 km

SiteMWDistance
The Elms
Solar Photovoltaics · Operational
10.43.4 km
Feldon Vale Solar Farm
Solar Photovoltaics · Operational
49.93.7 km
Weddington Farm
Solar Photovoltaics · Operational
2.15.8 km
Tollgate Farm
Solar Photovoltaics · Operational
4.36 km
Newbold Pacey Solar Farm�
Solar Photovoltaics · Operational
28.76.1 km
Eastfields Farm, Deppers Bridge - Solar Farm
Solar Photovoltaics · Under Construction
34.86.2 km
Eastfields Farm, Harbury - Battery Storage
Battery · Under Construction
6.3 km
Ufton
Landfill Gas · Operational
16.5 km

How big is Banbury Road, Gaydon - Solar Array?

Banbury Road, Gaydon - Solar Array has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Banbury Road, Gaydon - Solar Array?

REPD records the operator as Jaguar Land Rover Manufacturing. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Banbury Road, Gaydon - Solar Array approved and built?

The application was submitted on 2022-11-21. Permission was granted on 2023-03-23, 4 months later. The site became operational on 2025-08-01, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10016.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council