Stratford-on-Avon has decided 36 solar farms and approved 94% of them, taking a median of 3.7 months to decide. Consented capacity: 534 MW. 4 applications still awaiting a decision.

94%
Approved
34 granted · 2 refused
3.7 mo
Median decision
UK 2.3 mo
534 MW
Consented
17 MW refused
5
Appeals
4 allowed on appeal

How Stratford-on-Avon compares

Against the 298 UK authorities with 5+ solar decisions, Stratford-on-Avon sits in the 38th percentile for approval rate (1 points above the England average) and the 19th percentile for speed.

Decisions by year

510Approved — 3 (2014)Refused — 1 (2014)414Approved — 3 (2015)Refused — 1 (2015)415Approved — 3 (2016)316Approved — 1 (2017)117Approved — 1 (2020)120Approved — 3 (2021)321Approved — 5 (2022)522Approved — 7 (2023)723Approved — 2 (2024)224Approved — 5 (2025)525
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (42)

SchemeMWStatusDecided
Poolhead Lane, Earlswood - Solar panels
SNRG · 25/02011/PVN · 1.1 mo to decide
0.26Awaiting Construction2025-09-22
Moreton Morrell - Solar PV
Innova Renewables Limited · 24/02072/FUL · 10.3 mo to decide
20Awaiting Construction2025-07-17
Castle Farm Recreation Ground, Fishponds Road - Solar panels
Warwick District Council · W/25/0181 · 1.8 mo to decide
Awaiting Construction2025-04-06
Morrisons, Alcester Road - Solar Photovoltaic Panels
Morrisons · 25/00266/PVN · 1.8 mo to decide
0.31Awaiting Construction2025-04-01
Birmingham And Solihull Rugby Club, Forshaw Heath Lane - Solar Panels
Birmingham & Solihull Rugby Football Club · 24/03248/FUL
1.2Application Submitted2025-02-05
Larkstoke Farm, Admington Road - Solar Panels
G W Wilson & Sons · 24/03027/PVN · 1.8 mo to decide
0.19Awaiting Construction2025-02-04
Aston Martin Lagonda, Banbury Road - Solar panels
Aston Martin Head Office · 24/02075/PVN · 1.8 mo to decide
5.2Awaiting Construction2024-10-10
Aston Martin Lagonda, Banbury Road - Solar panels
Aston Martin Head Office · 24/01520/PVN
5.2Revised2024-08-12
Stratford Healthcare, Arden Street - Solar Panels
Assura Plc · 23/03411/PVN · 2.9 mo to decide
0.18Awaiting Construction2024-03-14
National Farmers Union, Tiddington Road - Solar PV
Ineco Energy · 23/03018/PVN · 1.4 mo to decide
0.23Awaiting Construction2023-12-21
Drayton Manor Farm, Alcester Road - Solar Farm Phase 2
Drayton Stratford · 23/00039/FUL · 8.2 mo to decide
32Awaiting Construction2023-11-07
Priors Marston Road, Hellidon - Solar Panels
Interesting Hotels Limited · 23/02136/FUL · 2.6 mo to decide
0.32Awaiting Construction2023-10-27
Middle Road Farm - Solar Farm & Battery Storage
Leicestershire Solar 1 Limited /Novergy · 23/01305/FUL · 3.4 mo to decide
49.99Awaiting Construction2023-08-18
Sherbourne - Solar Farm
Namene Solar · W/23/0150 · 6.4 mo to decide
25Awaiting Construction2023-08-16
Tything Road East, Kinwarton - Solar Panels
Roba Metals Limited · 23/01394/PVN
Application Submitted2023-05-31
Atherstone Hill Solar Farm
Elgin Energy Services · 22/03309/FUL · 2.4 mo to decide
26Awaiting Construction2023-04-11
Banbury Road, Gaydon - Solar Array
Jaguar Land Rover Manufacturing · 22/03361/FUL · 4 mo to decide
18Operational2023-03-23
Feldon Vale Solar Farm
Low Carbon · 22/02442/FUL
49.9Operational2023-01-23
Crimscote Solar Farm and Storage Project
Regener8 SPV1 Limited · 21/02017/FUL · 17.4 mo to decide
49.99Under Construction2022-11-29
Millennium Hatchery, Henley Road - Solar Panels
Hy-Line UK · 22/02594/PVN · 1.8 mo to decide
0.43Awaiting Construction2022-10-24
Newbold Pacey Solar Farm�
Innova Renewables / ISGRenewables · 22/00003/FUL · 6.5 mo to decide
28.7Operational2022-08-24
Ashorne Hill - Solar Farm
JBM Solar Projects Limited · W/21/1801 · 10.3 mo to decide
49.99Awaiting Construction2022-08-03
Gaydon Road, Bishops Itchington - Solar Photovoltaic Panels
WE Bates Limited · 22/00449/PVN · 2.2 mo to decide
0.21Awaiting Construction2022-04-19
Middle Road Farm - Solar Farm & Battery Storage
Leicestershire Solar 1 Limited · 22/00001/FUL
49.99Revised2022-01-04
British Film Institute - Solar Arrays
British Film Institute · 21/02952/FUL · 1.8 mo to decide
0.16Awaiting Construction2021-12-21
Eastfields Farm, Deppers Bridge - Solar Farm
Vantage RE · 21/02448/FUL · 0.9 mo to decide
34.8Under Construction2021-08-26
Feldon Vale Solar Farm
Low Carbon Limited · 20/02839/FUL · 10 mo to decide
49.9Awaiting Construction2021-08-13
Lower Farm
Codemaster Software Co · 18/03187/FUL · 23.3 mo to decide
0.5Under Construction2020-10-08
Lower Skilts Farm
Private Developer · 19/03523/FUL
0.5Application Withdrawn2020-06-16
Land at Radbrook Pastures
TGC Renewables/NESF · 15/00588/FUL · 27.5 mo to decide
20.7Planning Permission Expired2017-08-10
Bascote Road Solar Farm
TGC Renewables · 15/01740/FUL · 15.1 mo to decide
4.6Planning Permission Expired2016-09-05
Weddington Farm
Green Switch Solutions/Belvedere Energy Developments - Liquidated · 15/02717/FUL · 11.7 mo to decide
2.1Operational2016-09-05
Blackwell Grange Solar Farm
Conergy · 14/01732/FUL · 19.3 mo to decide
5Operational2016-03-01
Land On The East Side Of Fosse Way
Anesco · 15/02716/FUL · 4.2 mo to decide
10Operational2015-11-27
Solar Farm at Fields Farm (Phase 2)
Foresight Group (TGC Renewables) · 15/00767/FUL · 3.4 mo to decide
3.8Abandoned2015-06-29
Solar Farm at Fields Farm (Phase 1)
Foresight Group (TGC Renewables) · 15/00767/FUL · 3.4 mo to decide
5Operational2015-06-29
Drayton Manor Farm
Anesco · 15/00326/FUL · 4.2 mo to decide
25Operational2015-06-08
Park Farm (Claverdon)
BERTY 003 · 14/02034/FUL · 5.8 mo to decide
7.5Appeal Refused2015-03-12
Salford Lodge
AR Partners · 14/02463/FUL · 3 mo to decide
5Operational2014-12-11
The Elms
Foresight Solar Fund · 14/02341/FUL · 2.8 mo to decide
10.4Operational2014-11-27
Burton Farm
Quercus Renewable Holding 2 · 14/00536/FUL · 4.7 mo to decide
4.4Operational2014-07-10
Deppers Bridge
Solar Power South · 13/02689/FUL · 5.7 mo to decide
9Application Refused2014-04-09

Does Stratford-on-Avon approve solar farms?

Yes — of the 36 solar farms Stratford-on-Avon has decided, 94% were approved (34 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Stratford-on-Avon?

The median time from application to decision is 3.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Stratford-on-Avon consented?

534 MW has been consented across 34 approved schemes, with 17 MW refused. A further 4 applications awaits a decision.

Other technologies in Stratford-on-Avon

Battery storage in Stratford-on-AvonOnshore wind in Stratford-on-Avon

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.