Renewable planning › Solar › Stratford-on-Avon
Solar planning in Stratford-on-Avon
Stratford-on-Avon has decided 36 solar farms and approved 94% of them, taking a median of 3.7 months to decide. Consented capacity: 534 MW. 4 applications still awaiting a decision.
How Stratford-on-Avon compares
Against the 298 UK authorities with 5+ solar decisions, Stratford-on-Avon sits in the 38th percentile for approval rate (1 points above the England average) and the 19th percentile for speed.
Decisions by year
Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (42)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Poolhead Lane, Earlswood - Solar panels SNRG · 25/02011/PVN · 1.1 mo to decide | 0.26 | Awaiting Construction | 2025-09-22 |
Moreton Morrell - Solar PV Innova Renewables Limited · 24/02072/FUL · 10.3 mo to decide | 20 | Awaiting Construction | 2025-07-17 |
Castle Farm Recreation Ground, Fishponds Road - Solar panels Warwick District Council · W/25/0181 · 1.8 mo to decide | — | Awaiting Construction | 2025-04-06 |
Morrisons, Alcester Road - Solar Photovoltaic Panels Morrisons · 25/00266/PVN · 1.8 mo to decide | 0.31 | Awaiting Construction | 2025-04-01 |
Birmingham And Solihull Rugby Club, Forshaw Heath Lane - Solar Panels Birmingham & Solihull Rugby Football Club · 24/03248/FUL | 1.2 | Application Submitted | 2025-02-05 |
Larkstoke Farm, Admington Road - Solar Panels G W Wilson & Sons · 24/03027/PVN · 1.8 mo to decide | 0.19 | Awaiting Construction | 2025-02-04 |
Aston Martin Lagonda, Banbury Road - Solar panels Aston Martin Head Office · 24/02075/PVN · 1.8 mo to decide | 5.2 | Awaiting Construction | 2024-10-10 |
Aston Martin Lagonda, Banbury Road - Solar panels Aston Martin Head Office · 24/01520/PVN | 5.2 | Revised | 2024-08-12 |
Stratford Healthcare, Arden Street - Solar Panels Assura Plc · 23/03411/PVN · 2.9 mo to decide | 0.18 | Awaiting Construction | 2024-03-14 |
National Farmers Union, Tiddington Road - Solar PV Ineco Energy · 23/03018/PVN · 1.4 mo to decide | 0.23 | Awaiting Construction | 2023-12-21 |
Drayton Manor Farm, Alcester Road - Solar Farm Phase 2 Drayton Stratford · 23/00039/FUL · 8.2 mo to decide | 32 | Awaiting Construction | 2023-11-07 |
Priors Marston Road, Hellidon - Solar Panels Interesting Hotels Limited · 23/02136/FUL · 2.6 mo to decide | 0.32 | Awaiting Construction | 2023-10-27 |
Middle Road Farm - Solar Farm & Battery Storage Leicestershire Solar 1 Limited /Novergy · 23/01305/FUL · 3.4 mo to decide | 49.99 | Awaiting Construction | 2023-08-18 |
Sherbourne - Solar Farm Namene Solar · W/23/0150 · 6.4 mo to decide | 25 | Awaiting Construction | 2023-08-16 |
Tything Road East, Kinwarton - Solar Panels Roba Metals Limited · 23/01394/PVN | — | Application Submitted | 2023-05-31 |
Atherstone Hill Solar Farm Elgin Energy Services · 22/03309/FUL · 2.4 mo to decide | 26 | Awaiting Construction | 2023-04-11 |
Banbury Road, Gaydon - Solar Array Jaguar Land Rover Manufacturing · 22/03361/FUL · 4 mo to decide | 18 | Operational | 2023-03-23 |
Feldon Vale Solar Farm Low Carbon · 22/02442/FUL | 49.9 | Operational | 2023-01-23 |
Crimscote Solar Farm and Storage Project Regener8 SPV1 Limited · 21/02017/FUL · 17.4 mo to decide | 49.99 | Under Construction | 2022-11-29 |
Millennium Hatchery, Henley Road - Solar Panels Hy-Line UK · 22/02594/PVN · 1.8 mo to decide | 0.43 | Awaiting Construction | 2022-10-24 |
Newbold Pacey Solar Farm� Innova Renewables / ISGRenewables · 22/00003/FUL · 6.5 mo to decide | 28.7 | Operational | 2022-08-24 |
Ashorne Hill - Solar Farm JBM Solar Projects Limited · W/21/1801 · 10.3 mo to decide | 49.99 | Awaiting Construction | 2022-08-03 |
Gaydon Road, Bishops Itchington - Solar Photovoltaic Panels WE Bates Limited · 22/00449/PVN · 2.2 mo to decide | 0.21 | Awaiting Construction | 2022-04-19 |
Middle Road Farm - Solar Farm & Battery Storage Leicestershire Solar 1 Limited · 22/00001/FUL | 49.99 | Revised | 2022-01-04 |
British Film Institute - Solar Arrays British Film Institute · 21/02952/FUL · 1.8 mo to decide | 0.16 | Awaiting Construction | 2021-12-21 |
Eastfields Farm, Deppers Bridge - Solar Farm Vantage RE · 21/02448/FUL · 0.9 mo to decide | 34.8 | Under Construction | 2021-08-26 |
Feldon Vale Solar Farm Low Carbon Limited · 20/02839/FUL · 10 mo to decide | 49.9 | Awaiting Construction | 2021-08-13 |
Lower Farm Codemaster Software Co · 18/03187/FUL · 23.3 mo to decide | 0.5 | Under Construction | 2020-10-08 |
Lower Skilts Farm Private Developer · 19/03523/FUL | 0.5 | Application Withdrawn | 2020-06-16 |
Land at Radbrook Pastures TGC Renewables/NESF · 15/00588/FUL · 27.5 mo to decide | 20.7 | Planning Permission Expired | 2017-08-10 |
Bascote Road Solar Farm TGC Renewables · 15/01740/FUL · 15.1 mo to decide | 4.6 | Planning Permission Expired | 2016-09-05 |
Weddington Farm Green Switch Solutions/Belvedere Energy Developments - Liquidated · 15/02717/FUL · 11.7 mo to decide | 2.1 | Operational | 2016-09-05 |
Blackwell Grange Solar Farm Conergy · 14/01732/FUL · 19.3 mo to decide | 5 | Operational | 2016-03-01 |
Land On The East Side Of Fosse Way Anesco · 15/02716/FUL · 4.2 mo to decide | 10 | Operational | 2015-11-27 |
Solar Farm at Fields Farm (Phase 2) Foresight Group (TGC Renewables) · 15/00767/FUL · 3.4 mo to decide | 3.8 | Abandoned | 2015-06-29 |
Solar Farm at Fields Farm (Phase 1) Foresight Group (TGC Renewables) · 15/00767/FUL · 3.4 mo to decide | 5 | Operational | 2015-06-29 |
Drayton Manor Farm Anesco · 15/00326/FUL · 4.2 mo to decide | 25 | Operational | 2015-06-08 |
Park Farm (Claverdon) BERTY 003 · 14/02034/FUL · 5.8 mo to decide | 7.5 | Appeal Refused | 2015-03-12 |
Salford Lodge AR Partners · 14/02463/FUL · 3 mo to decide | 5 | Operational | 2014-12-11 |
The Elms Foresight Solar Fund · 14/02341/FUL · 2.8 mo to decide | 10.4 | Operational | 2014-11-27 |
Burton Farm Quercus Renewable Holding 2 · 14/00536/FUL · 4.7 mo to decide | 4.4 | Operational | 2014-07-10 |
Deppers Bridge Solar Power South · 13/02689/FUL · 5.7 mo to decide | 9 | Application Refused | 2014-04-09 |
Does Stratford-on-Avon approve solar farms?
Yes — of the 36 solar farms Stratford-on-Avon has decided, 94% were approved (34 granted, 2 refused). The UK-wide rate for solar is 93%.
How long does a solar farm application take in Stratford-on-Avon?
The median time from application to decision is 3.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much solar capacity has Stratford-on-Avon consented?
534 MW has been consented across 34 approved schemes, with 17 MW refused. A further 4 applications awaits a decision.
Other technologies in Stratford-on-Avon
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.