Novarly ParcelRenewable sites

Renewable sitesBrickyard Barn

Brickyard Barn

Brickyard Barn is operational in Warwick with a recorded capacity of 4.1 MW, and has been generating since 2014-11-27.

4.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-11-27
Solar Photovoltaics
Technology
Sun Glow Power
Warwick
Authority
England

Planning and build timeline

Application submitted2013-11-15
Permission granted2013-12-20
1 months after submission
Operational2014-11-27
11 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Warwick’s record on solar

Warwick has decided 18 solar farms and approved 83%, taking a median of 1.8 months. See every solar farm decision in Warwick

Other built sites within 15 km

SiteMWDistance
Tollgate Farm
Solar Photovoltaics · Operational
4.31.9 km
Wolseley National Distribution Centre
Solar Photovoltaics · Operational
22.9 km
Newbold Pacey Solar Farm�
Solar Photovoltaics · Operational
28.74.4 km
Land On The East Side Of Fosse Way
Solar Photovoltaics · Operational
105.1 km
Ufton
Landfill Gas · Operational
17.7 km
Banbury Road, Gaydon - Solar Array
Solar Photovoltaics · Operational
187.9 km
The Elms
Solar Photovoltaics · Operational
10.48.6 km
Eastfields Farm, Harbury - Battery Storage
Battery · Under Construction
8.7 km

How big is Brickyard Barn?

Brickyard Barn has a recorded installed capacity of 4.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Brickyard Barn?

REPD records the operator as Sun Glow Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Brickyard Barn approved and built?

The application was submitted on 2013-11-15. Permission was granted on 2013-12-20, 1 months later. The site became operational on 2014-11-27, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1519.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council