Ufton is an operational 1 MW landfill gas site in Stratford-on-Avon, generating since 26 November 1999. Planning permission was granted on 6 September 1999, 5 months after submission. Operator of record: Biffa.
Planning and build timeline
| Application submitted | 14 April 1999 |
| Permission granted | 6 September 1999 5 months after submission |
| Operational | 26 November 1999 3 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Stratford-on-Avon: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Ufton’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
- Local nature reserve — UFTON FIELDS
- SSSI — Ufton Fields SSSI
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | — | 1.3 km |
Solar Photovoltaics · Under Construction | 0.5 | 1.7 km |
Solar Photovoltaics · Under Construction | 34.8 | 1.7 km |
Solar Photovoltaics · Operational | 5 | 2.3 km |
Solar Photovoltaics · Operational | 10 | 2.6 km |
Solar Photovoltaics · Operational | 10.4 | 3.7 km |
Solar Photovoltaics · Operational | 2.1 | 4.1 km |
Solar Photovoltaics · Operational | 49.9 | 5.7 km |
How big is Ufton?
Ufton has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ufton?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ufton approved and built?
The application was submitted on 14 April 1999. Permission was granted on 6 September 1999, 5 months later. The site became operational on 26 November 1999, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 717.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode