Renewable sites › Ufton
Ufton
Ufton is operational in Stratford-on-Avon with a recorded capacity of 1 MW, and has been generating since 1999-11-26.
Planning and build timeline
| Application submitted | 1999-04-14 |
| Permission granted | 1999-09-06 5 months after submission |
| Operational | 1999-11-26 3 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
- Local nature reserve — UFTON FIELDS
- SSSI — Ufton Fields SSSI
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Eastfields Farm, Harbury - Battery Storage Battery · Under Construction | — | 1.3 km |
Lower Farm Solar Photovoltaics · Under Construction | 0.5 | 1.7 km |
Eastfields Farm, Deppers Bridge - Solar Farm Solar Photovoltaics · Under Construction | 34.8 | 1.7 km |
Solar Farm at Fields Farm (Phase 1) Solar Photovoltaics · Operational | 5 | 2.3 km |
Land On The East Side Of Fosse Way Solar Photovoltaics · Operational | 10 | 2.6 km |
The Elms Solar Photovoltaics · Operational | 10.4 | 3.7 km |
Weddington Farm Solar Photovoltaics · Operational | 2.1 | 4.1 km |
Feldon Vale Solar Farm Solar Photovoltaics · Operational | 49.9 | 5.7 km |
How big is Ufton?
Ufton has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ufton?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ufton approved and built?
The application was submitted on 1999-04-14. Permission was granted on 1999-09-06, 5 months later. The site became operational on 1999-11-26, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 717.