Renewable sites › Morfa Farm
Morfa Farm
Morfa Farm is operational in Vale of Glamorgan with a recorded capacity of 2 MW, and has been generating since 2016-12-19.
Planning and build timeline
| Application submitted | 2015-07-15 |
| Permission granted | 2015-11-20 4 months after submission |
| Operational | 2016-12-19 13 months after consent |
Vale of Glamorgan’s record on solar
Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rosedew Farm Solar Photovoltaics · Operational | 5 | 3.3 km |
Treguff Farm Solar Photovoltaics · Operational | 4.4 | 6.4 km |
Corntown Farm Solar Photovoltaics · Operational | 3.4 | 6.8 km |
West Hall Solar Farm Solar Photovoltaics · Operational | 7 | 7.1 km |
Llancadle Farm Solar Photovoltaics · Operational | 5 | 7.9 km |
Garn Solar Farm Solar Photovoltaics · Operational | 7.4 | 8.4 km |
SAS International, Unit 1 - Solar PV Panels Solar Photovoltaics · Under Construction | 0.8 | 8.4 km |
Land At Court Farm Solar Photovoltaics · Operational | 2.2 | 8.6 km |
How big is Morfa Farm?
Morfa Farm has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Morfa Farm?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Morfa Farm approved and built?
The application was submitted on 2015-07-15. Permission was granted on 2015-11-20, 4 months later. The site became operational on 2016-12-19, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1862.