Land At Court Farm is an operational 2.2 MW solar farm in Vale of Glamorgan, generating since 16 March 2016. Planning permission was granted on 5 June 2015, 4 months after submission. Operator of record: Sybac Solar International GmbH.

2.2 MW
Capacity
as recorded in REPD
Operational
Status
since 16 March 2016
Solar Photovoltaics
Technology
Sybac Solar International GmbH
Vale of Glamorgan
Authority
Wales

Planning and build timeline

Application submitted21 January 2015
Permission granted5 June 2015
4 months after submission
Operational16 March 2016
9 months after consent

Screening a site of your own?

RedlineUK · £39

Vale of Glamorgan approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land At Court Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Vale of Glamorgan’s record on solar

Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.81 km
Solar Photovoltaics · Operational
3.42.2 km
Solar Photovoltaics · Under Construction
1.36.4 km
Solar Photovoltaics · Operational
47 km
Solar Photovoltaics · Operational
157.6 km
Wind Onshore · Operational
9.47.6 km
Wind Onshore · Operational
128.4 km
Solar Photovoltaics · Operational
28.6 km

How big is Land At Court Farm?

Land At Court Farm has a recorded installed capacity of 2.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land At Court Farm?

REPD records the operator as Sybac Solar International GmbH. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land At Court Farm approved and built?

The application was submitted on 21 January 2015. Permission was granted on 5 June 2015, 4 months later. The site became operational on 16 March 2016, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1521.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode