Llancadle Farm
Llancadle Farm is an operational 5 MW solar farm in Vale of Glamorgan, generating since 15 December 2015. Planning permission was granted on 15 May 2015, 5 months after submission. Operator of record: Llancadle Solar Farm Ltd.
Planning and build timeline
| Application submitted | 7 December 2014 |
| Permission granted | 15 May 2015 5 months after submission |
| Operational | 15 December 2015 7 months after consent |
Screening a site of your own?
Vale of Glamorgan approves 96% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Llancadle Farm’s recorded coordinate — swap in your own postcode or coordinates.
Vale of Glamorgan’s record on solar
Vale of Glamorgan has decided 25 solar farms and approved 96%, taking a median of 4.2 months. See every solar farm decision in Vale of Glamorgan →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 7 | 1.8 km |
Solar Photovoltaics · Operational | 4.4 | 3.1 km |
Solar Photovoltaics · Operational | 7.5 | 4.3 km |
Solar Photovoltaics · Operational | 5 | 5.1 km |
Solar Photovoltaics · Operational | 7.4 | 5.2 km |
Solar Photovoltaics · Operational | 7 | 5.6 km |
Solar Photovoltaics · Operational | 6 | 5.8 km |
Solar Photovoltaics · Operational | 5 | 6 km |
How big is Llancadle Farm?
Llancadle Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Llancadle Farm?
REPD records the operator as Llancadle Solar Farm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Llancadle Farm approved and built?
The application was submitted on 7 December 2014. Permission was granted on 15 May 2015, 5 months later. The site became operational on 15 December 2015, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4940.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode