Renewable sitesMelton Waste Park

Melton Waste Park

Melton Waste Park is operational in East Riding of Yorkshire with a recorded capacity of 5 MW, and has been generating since 2017-03-01.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-01
Wind Onshore
Technology
Seneca Global Energy
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2015-02-03
Permission granted2015-04-20
2 months after submission
Operational2017-03-01
22 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on onshore wind

East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82%, taking a median of 7.8 months. See every onshore wind scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Melton Common Wind Cluster
Wind Onshore · Operational
50.5 km
Winterton Landfill Site
Landfill Gas · Operational
3.87.7 km
Winterton Landfill Site - Ground Mounted Solar PV Arrays
Solar Photovoltaics · Under Construction
58 km
Cottingham - Solar Farm
Solar Photovoltaics · Operational
58.1 km
Bonby Lane
Anaerobic Digestion · Operational
1.510.2 km
Roxby Gas to Energy
Landfill Gas · Operational
8.510.4 km
Brocklesby - Crosslands Lane
Anaerobic Digestion · Operational
3.510.9 km
Creyke Beck
Battery · Operational
49.911.7 km

How big is Melton Waste Park?

Melton Waste Park has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Melton Waste Park?

REPD records the operator as Seneca Global Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Melton Waste Park approved and built?

The application was submitted on 2015-02-03. Permission was granted on 2015-04-20, 2 months later. The site became operational on 2017-03-01, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4995.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council