Renewable planning › Onshore wind › East Riding of Yorkshire
Onshore wind planning in East Riding of Yorkshire
East Riding of Yorkshire has decided 55 onshore wind schemes and approved 82% of them, taking a median of 7.8 months to decide. Consented capacity: 592 MW. 10 applications still awaiting a decision.
How East Riding of Yorkshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, East Riding of Yorkshire sits in the 80th percentile for approval rate (14 points above the England average) and the 86th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (73)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Priest Close, Burton Road - Wind Turbine Yorkwold Pigpro Limited · 26/00228/PLF | 0.25 | Application Submitted | 2026-02-06 |
Great Kendale, Nafferton - Wind Turbine Peter BT Beal and Sons · 25/03411/PLF · 1.7 mo to decide | 0.5 | Awaiting Construction | 2026-01-30 |
Burton Road, Burton Pidsea - Wind Turbine Yorkwold Pigpro Limited · 26/00229/PLF | 0.25 | Application Submitted | 2026-01-29 |
Burton Road - Wind Turbines E Falkingham & Sons Limited · 25/03235/PLF · 1.8 mo to decide | 0.25 | Awaiting Construction | 2026-01-14 |
Burton Road, Burton Pidsea - Wind Turbine Yorkwold Pigpro Limited · 25/03121/PLF · 1.8 mo to decide | 0.25 | Application Refused | 2026-01-13 |
Cowden Magna Farm, Cowden - Wind Turbine Yorkwold Pigpro Limited · 25/03282/PLF · 1.8 mo to decide | 0.25 | Awaiting Construction | 2026-01-12 |
Southfield House Farm, Hornsea Road - Wind Turbine Private Developer · 25/03601/PLF | 0.22 | Application Submitted | 2026-01-05 |
Market Weighton Road, Middleton On The Wolds -Wind Turbine T Soanes And Son Farming · 25/02618/PLF · 3.1 mo to decide | 0.25 | Awaiting Construction | 2025-12-19 |
Weighton Road, Sancton - Wind Turbine AEW Wind Limited · 25/03147/PLF · 1.4 mo to decide | 0.23 | Awaiting Construction | 2025-12-18 |
Low Cowlam Farm, Driffield Road - Wind Turbines E T Robinson & Sons · 25/03045/PLF · 1.7 mo to decide | 0.5 | Awaiting Construction | 2025-12-15 |
Weighton Wold, Arras Hill - Wind Turbine R & J Farms · 25/02860/PLF · 1.8 mo to decide | 0.25 | Awaiting Construction | 2025-12-01 |
Raven Hill Farm, Langtoft Road - Wind Turbines S J Savile & Sons Limited · 25/02716/PLF · 1.8 mo to decide | 250 | Awaiting Construction | 2025-11-18 |
Towthorpe Manor Farm, Towthorpe Road - Wind turbine E R Megginson And Sons Limited · 25/02330/PLF · 1.6 mo to decide | 0.25 | Awaiting Construction | 2025-10-10 |
Grove Farm, Main Street - Wind Turbines TA & PJ Stephenson Limited · 25/00726/PLF · 5.5 mo to decide | 0.45 | Awaiting Construction | 2025-10-09 |
Tuft Hill Farm, Woldgate - Wind Turbine Harrison Farm Services Limited · 25/01718/PLF · 1.9 mo to decide | 0.23 | Awaiting Construction | 2025-08-27 |
Little Pockthorpe Farm, Pockthorpe Lane - Wind Turbines Pockthorpe Renewables Limited · 25/00608/STPLF · 3.9 mo to decide | 0.23 | Awaiting Construction | 2025-07-31 |
Middledale Heights, Langtoft Road - Wind Turbines R Byas · 25/01169/PLF · 1.8 mo to decide | 0.45 | Awaiting Construction | 2025-07-10 |
Pockthorpe Hall, Nafferton - Wind Turbine DP Morgan Unlimited · 25/00840/PLF · 1.7 mo to decide | — | Awaiting Construction | 2025-06-23 |
Braffords Farm, Riplingham Road - Wind Turbine CWE V27 Limited · 23/03527/PLF · 7 mo to decide | 0.33 | Awaiting Construction | 2024-07-11 |
Melton - Wind Turbines Omya UK Limited · 22/01302/CME · 21.1 mo to decide | 3 | Awaiting Construction | 2024-02-12 |
North Farm Wind Turbines, Thorpe Le Street - Wind Turbine Sellmor Farming Limited · 22/03694/PLF · 14.1 mo to decide | 1 | Awaiting Construction | 2024-02-02 |
Melton Common Wind Cluster Melton Wind Limited · 23/01982/STPLFE | 4.6 | Application Submitted | 2023-08-17 |
Burton Fleming Grange, Wold Newton Road - Wind Turbine Stephen B Wells Limited · 23/00580/PLF · 3.6 mo to decide | 0.66 | Awaiting Construction | 2023-08-10 |
Skipsea Lane, Dunnington - Wind Farm Manor Farm Feeds · 22/00443/STPLF · 7.2 mo to decide | 4.2 | Awaiting Construction | 2022-10-21 |
Bonwick Whirlwind Renewables · 15/00517/STPLFE · 23.8 mo to decide | 17 | Application Refused | 2017-02-27 |
Withernwick extension Energiekontor UK · 14/01919/STPLFE · 29.9 mo to decide | 8.2 | Operational | 2016-12-19 |
Melton Common Wind Cluster Melton Wind Limited · 14/01499/STPLFE · 19.8 mo to decide | 2.3 | Awaiting Construction | 2016-02-05 |
Melton Common Wind Cluster Seneca Global Energy · 14/01499/STPLFE · 19.8 mo to decide | 6.9 | Revised | 2016-02-05 |
Rotsea Wind Farm Renewable Energy Systems (RES) · 13/03606/STPLFE · 23.7 mo to decide | 6.9 | Application Refused | 2015-11-05 |
Lissett Airfield Wind Farm Extension Energiekontor UK · 13/03625/STPLFE · 21.2 mo to decide | 12.5 | Appeal Withdrawn | 2015-08-06 |
High Wood Wind Farm EDF Energy Renewables · 15/00315/STPLFE | 25 | Application Withdrawn | 2015-08-03 |
Bagletts Wind Farm Lantanier UK · 14/03106/STPLFE | 6.9 | Application Withdrawn | 2015-07-15 |
Melton Waste Park Seneca Global Energy · 14/03951/STPLFE · 2.5 mo to decide | 5 | Operational | 2015-04-20 |
Skeffling Wind Farm BT - Wind for Change · 11/05745/STPLFE | 11.5 | Application Withdrawn | 2015-03-19 |
Rawcliffe Bridge Wind Farm Airvolution Energy · 13/04183/STPLFE · 12.6 mo to decide | 10 | Application Refused | 2015-02-24 |
Goole Fields ll Wind Farm RWE Npower Renewables · 11/05923/STPLFE · 28.5 mo to decide | 34.9 | Operational | 2014-05-22 |
Land South Of Demming Farm Airvolution Energy · 13/00316/STPLFE · 10.7 mo to decide | 8 | Application Refused | 2014-01-27 |
Far Marsh Farm Private Developer · 12/04962/STPLFE · 12.3 mo to decide | 7.5 | Operational | 2013-12-24 |
Melton Common Wind Cluster Seneca Global Energy · 13/01806/STPLFE · 6.2 mo to decide | 5 | Operational | 2013-12-19 |
Spaldington Common wind cluster Volkswind UK Ltd · 13/00698/STPLFE · 5.5 mo to decide | 5 | Application Refused | 2013-09-23 |
River Valley Wind farm RWE npower · 12/04561/STPLFE · 9.2 mo to decide | 18 | Application Refused | 2013-08-13 |
Fraisthorpe Wind Farm Octopus Investments · 12/00640/STPLFE · 11.4 mo to decide | 29.7 | Operational | 2013-01-22 |
Thornholme Wind Farm Wind Prospect Developments · 11/03999/STPLFE · 15.4 mo to decide | 12 | Appeal Refused | 2012-12-19 |
The Limes Wind Turbines Broadview Energy · 11/01980/STPLFE · 18.4 mo to decide | 1.7 | Operational | 2012-11-19 |
Celcon Blocks Ltd Ecotricity / Next Generation · 09/02681/STPLF · 38.4 mo to decide | 2 | Operational | 2012-10-17 |
Gallymoor Landfill Site FCC Environment · 11/00537/STPLF · 16.9 mo to decide | 1.8 | Awaiting Construction | 2012-07-10 |
Far Marsh Farm Private Developer · 11/05896/STPLFE | 7.5 | Revised | 2012-04-04 |
Carnaby FCC Environment · 10/04753/STPLFE · 14.8 mo to decide | 6 | Awaiting Construction | 2012-02-20 |
Spaldington Airfield Falck Renewables · 09/04550/STPLFE · 22.3 mo to decide | 12.5 | Operational | 2011-09-29 |
Charity Farm Npower · 09/02564/STPLFE | 32 | Application Withdrawn | 2011-03-01 |
Sancton Hill REG Windpower (previously Cornwall Light and Power) · 10/02080/STPLFE · 8.8 mo to decide | 10 | Operational | 2011-02-10 |
Aire & Calder Wind Farm E.ON UK · 05/05933/STPLFE | 45 | Application Withdrawn | 2010-11-25 |
Spaldington Common Windfarm Volkswind UK Ltd · 09/04568/STPLFE · 10.1 mo to decide | 16.1 | Revised | 2010-09-22 |
Roos Wind Farm (Resubmission) Renewable Energy Systems (RES) · 08/05692/STPLFE · 15.7 mo to decide | 17.1 | Operational | 2010-05-13 |
Sober Hill Wind Farm West Coast Energy · 08/04816/STPLFE · 17.5 mo to decide | 15 | Operational | 2010-03-19 |
Tedder Hill Wind cluster Ventient (formerly Infinis) · 06/03729/STPLF · 44.6 mo to decide | 7.5 | Operational | 2010-01-28 |
Monkwith Wind Farm Energiekontor UK · 09/02000/STPLFE · 7.3 mo to decide | 6.9 | Appeal Refused | 2010-01-21 |
Sixpenny Wood Windfarm Greencoat UK Wind · 07/04680/STPLFE · 28.6 mo to decide | 33 | Operational | 2009-12-08 |
Burton Pidsea (Wadworth Hill) Wind Farm Aeolian Holderness Ltd · 08/02928/STPLFE · 15.2 mo to decide | 10.2 | Operational | 2009-09-03 |
Sancton Hill Cornwall Light and Power · 08/05723/STPFE · 3.2 mo to decide | 10 | Revised | 2009-03-19 |
Hall Farm Routh John Laing Environmental Assets Group/REG Power Management · 06/08470/STPLFE · 27.8 mo to decide | 24.6 | Operational | 2009-02-17 |
Withernwick Energiekontor UK · 08/01964/STPLFE · 5 mo to decide | 18 | Operational | 2008-09-02 |
Monkwith Wind Farm Energiekontor UK · 07/01140/STPLFE · 7.8 mo to decide | 14 | Revised | 2007-10-18 |
Withernwick (withdrawn) Energiekontor UK · 07/02271/STPLFE | 25 | Application Withdrawn | 2007-10-17 |
Lissett Airfield Wind Farm Novera Energy · 06/05618/STPLFE · 7.5 mo to decide | 30 | Operational | 2007-02-22 |
Loftsome Bridge Yorkshire Water · 06/05245/STPLF · 7.1 mo to decide | 1.3 | Operational | 2007-01-31 |
Croda Chemicals Europe Croda Chemicals · 16999M · 5.7 mo to decide | 3 | Operational | 2006-10-16 |
Saltend Wind Turbine Yorkshire Water · 05/08754/STPLF · 2.9 mo to decide | 1.3 | Operational | 2006-03-06 |
Outstray Farm Wind Project Farm Energy (The Wind Company Ltd) · 362/10019 | 1.8 | Application Withdrawn | 2005-08-05 |
Goole Fields RWE npower · 03/01987 · 5 mo to decide | 32.8 | Operational | 2003-09-01 |
Eastfield Farm Wind Farm Renewable Energy Systems (RES) · 347/10029A · 24.1 mo to decide | 11.4 | Application Refused | 2000-09-11 |
Out Newton Wind Farm Powergen Renewables Developments Ltd · 341/10033 · 22.2 mo to decide | 9 | Operational | 2000-09-11 |
Sober Hill Wind Farm West Coast Energy · 3.4 mo to decide | 1.5 | Revised | 1995-12-14 |
Does East Riding of Yorkshire approve onshore wind schemes?
Yes — of the 55 onshore wind schemes East Riding of Yorkshire has decided, 82% were approved (45 granted, 10 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in East Riding of Yorkshire?
The median time from application to decision is 7.8 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has East Riding of Yorkshire consented?
592 MW has been consented across 45 approved schemes, with 95 MW refused. A further 10 applications awaits a decision.
Other technologies in East Riding of Yorkshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.