Novarly ParcelRenewable sites

Renewable sitesMarston Vale Country Park Wind Turbine

Marston Vale Country Park Wind Turbine

Marston Vale Country Park Wind Turbine is an operational 1.5 MW onshore wind farm in Central Bedfordshire, generating since 1 May 2014. Planning permission was granted on 1 February 2012, 3 months after submission. Operator of record: Blue Energy.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2014
Wind Onshore
Technology
Blue Energy
Central Bedfordshire
Authority
England

Planning and build timeline

Application submitted11 November 2011
Permission granted1 February 2012
3 months after submission
Operational1 May 2014
27 months after consent

Screening a site of your own?

RedlineUK · £39

Central Bedfordshire approves 86% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Marston Vale Country Park Wind Turbine’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Central Bedfordshire’s record on onshore wind

Central Bedfordshire has decided 7 onshore wind schemes and approved 86%, taking a median of 8.6 months. See every onshore wind scheme decision in Central Bedfordshire

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Operational
651.4 km
Landfill Gas · Operational
10.71.9 km
Landfill Gas · Operational
113.7 km
Landfill Gas · Operational
113.8 km
Solar Photovoltaics · Operational
15.3 km
Landfill Gas · Operational
1.86.1 km
Solar Photovoltaics · Operational
0.446.6 km
Biomass (dedicated) · Operational
166.6 km

How big is Marston Vale Country Park Wind Turbine?

Marston Vale Country Park Wind Turbine has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marston Vale Country Park Wind Turbine?

REPD records the operator as Blue Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marston Vale Country Park Wind Turbine approved and built?

The application was submitted on 11 November 2011. Permission was granted on 1 February 2012, 3 months later. The site became operational on 1 May 2014, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3890.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode