Elstow Landfill Site

Elstow Landfill Site is operational in Bedford with a recorded capacity of 1.8 MW, and has been generating since 1996-07-08.

1.8 MW
Capacity
as recorded in REPD
Operational
Status
since 1996-07-08
Landfill Gas
Technology
Renewable Power Generation Ltd
Bedford
Authority
England

Planning and build timeline

Application submitted1995-01-09
Permission granted1995-06-23
5 months after submission
Operational1996-07-08
13 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Elstow Landfill Site
Solar Photovoltaics · Under Construction
5.53.2 km
L'Field Stewartby Landfill Site
Landfill Gas · Operational
10.74.3 km
Rookery South
EfW Incineration · Operational
654.9 km
Marston Vale Country Park Wind Turbine
Wind Onshore · Operational
1.56.1 km
Clapham solar farm
Solar Photovoltaics · Operational
7.58.2 km
Brogborough Phase IV
Landfill Gas · Operational
119.5 km
Brogborough Phase III
Landfill Gas · Operational
119.8 km
Twinwoods Heat & Power CHP
EfW Incineration · Operational
3.410 km

How big is Elstow Landfill Site?

Elstow Landfill Site has a recorded installed capacity of 1.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Elstow Landfill Site?

REPD records the operator as Renewable Power Generation Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Elstow Landfill Site approved and built?

The application was submitted on 1995-01-09. Permission was granted on 1995-06-23, 5 months later. The site became operational on 1996-07-08, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 511.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council