Brogborough Phase III is an operational 11 MW landfill gas site in Central Bedfordshire, generating since 29 April 2001. Planning permission was granted on 7 August 1990, 4 months after submission. Operator of record: Waste Recycling Group.
Planning and build timeline
| Application submitted | 19 April 1990 |
| Permission granted | 7 August 1990 4 months after submission |
| Operational | 29 April 2001 129 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Central Bedfordshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Brogborough Phase III’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 11 | 0.4 km |
Solar Photovoltaics · Operational | 1 | 2.4 km |
Biomass (dedicated) · Operational | 16 | 3.6 km |
Solar Photovoltaics · Operational | 0.44 | 3.6 km |
Solar Photovoltaics · Operational | 0.88 | 3.8 km |
Wind Onshore · Operational | 1.5 | 3.8 km |
Solar Photovoltaics · Operational | 1.97 | 4.9 km |
EfW Incineration · Operational | 65 | 4.9 km |
How big is Brogborough Phase III?
Brogborough Phase III has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brogborough Phase III?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brogborough Phase III approved and built?
The application was submitted on 19 April 1990. Permission was granted on 7 August 1990, 4 months later. The site became operational on 29 April 2001, 129 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 515.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode