Renewable sites › Brogborough Phase III
Brogborough Phase III
Brogborough Phase III is operational in Central Bedfordshire with a recorded capacity of 11 MW, and has been generating since 2001-04-29.
Planning and build timeline
| Application submitted | 1990-04-19 |
| Permission granted | 1990-08-07 4 months after submission |
| Operational | 2001-04-29 129 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brogborough Phase IV Landfill Gas · Operational | 11 | 0.4 km |
Cranfield Airfield Solar Photovoltaics · Operational | 1 | 2.4 km |
Goosey Lodge Industrial Estate Biomass (dedicated) · Operational | 16 | 3.6 km |
Cranfield University - Solar Farm Solar Photovoltaics · Operational | 0.44 | 3.6 km |
University Way, Cranfield - Solar Array Solar Photovoltaics · Operational | 0.88 | 3.8 km |
Marston Vale Country Park Wind Turbine Wind Onshore · Operational | 1.5 | 3.8 km |
Harvie Card Way - Solar panels Solar Photovoltaics · Operational | 1.97 | 4.9 km |
Rookery South EfW Incineration · Operational | 65 | 4.9 km |
How big is Brogborough Phase III?
Brogborough Phase III has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brogborough Phase III?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brogborough Phase III approved and built?
The application was submitted on 1990-04-19. Permission was granted on 1990-08-07, 4 months later. The site became operational on 2001-04-29, 129 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 515.
Novarly Parcel · official public data, read properly · parcel.novarly.com