Cranfield Airfield is an operational 1 MW solar farm in Central Bedfordshire, generating since 1 September 2018. Planning permission was granted on 28 May 2020, 32 months after submission. Operator of record: Cranfield Univsersity.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 September 2018
Solar Photovoltaics
Technology
Cranfield Univsersity
Central Bedfordshire
Authority
England

Planning and build timeline

Application submitted12 October 2017
Permission granted28 May 2020
32 months after submission
Operational1 September 2018

Screening a site of your own?

RedlineUK · £39

Central Bedfordshire approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cranfield Airfield’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Central Bedfordshire’s record on solar

Central Bedfordshire has decided 32 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Central Bedfordshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.441.3 km
Solar Photovoltaics · Operational
0.881.6 km
Landfill Gas · Operational
112.2 km
Landfill Gas · Operational
112.4 km
Solar Photovoltaics · Operational
1.974.2 km
Biomass (dedicated) · Operational
165.2 km
Wind Onshore · Operational
1.55.3 km
EfW Incineration · Operational
655.9 km

How big is Cranfield Airfield?

Cranfield Airfield has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cranfield Airfield?

REPD records the operator as Cranfield Univsersity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cranfield Airfield approved and built?

The application was submitted on 12 October 2017. Permission was granted on 28 May 2020, 32 months later. The site became operational on 1 September 2018.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6603.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode