Renewable planning › Onshore wind › Central Bedfordshire
Onshore wind planning in Central Bedfordshire
Central Bedfordshire has decided 7 onshore wind schemes and approved 86% of them, taking a median of 8.6 months to decide. Consented capacity: 29 MW.
⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.
How Central Bedfordshire compares
Against the 75 UK authorities with 5+ onshore wind decisions, Central Bedfordshire sits in the 88th percentile for approval rate (18 points above the England average) and the 82nd percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (7)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Eyeworth Lodge Farm, Eyeworth - Wind Turbine Lodge Farm Poultry Limited · CB/24/01849/FULL · 8.6 mo to decide | 0.22 | Awaiting Construction | 2025-03-14 |
Astral Green - Wind Turbine, Solar Array & Battery Energy Storage System Arnold White Estates Limited · CB/23/03278/FULL · 4.5 mo to decide | 1.5 | Awaiting Construction | 2024-04-08 |
Checkley Wood Farm AW Group · CB/16/01389/FULL · 16.8 mo to decide | 4.1 | Operational | 2017-09-13 |
Brogborough Landfill Site FCC Environment · CB/14/00925/FULL · 3.5 mo to decide | 5.4 | Application Refused | 2014-07-03 |
Marston Vale Country Park Wind Turbine Blue Energy · CB/11/04077/FULL · 2.7 mo to decide | 1.5 | Operational | 2012-02-01 |
Langford Wind Farm Co-operative Group · 09/00118/FULL · 35.2 mo to decide | 20 | Operational | 2012-01-19 |
Double Arches Quarry Wind Turbine Arnold White Estates (AWE Renewables) · CB/10/03034/FULL · 10.8 mo to decide | 1.5 | Operational | 2011-08-02 |
Does Central Bedfordshire approve onshore wind schemes?
Yes — of the 7 onshore wind schemes Central Bedfordshire has decided, 86% were approved (6 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.
How long does a onshore wind scheme application take in Central Bedfordshire?
The median time from application to decision is 8.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Central Bedfordshire consented?
29 MW has been consented across 6 approved schemes, with 5 MW refused. There are no applications currently awaiting a decision.
Other technologies in Central Bedfordshire
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.