Renewable sitesMarsh Farm (Farm AD)

Marsh Farm (Farm AD)

Marsh Farm (Farm AD) is operational in Boston with a recorded capacity of 1.4 MW, and has been generating since 2011-02-24.

1.4 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-02-24
Anaerobic Digestion
Technology
Staples Brothers
Boston
Authority
England

Planning and build timeline

Application submitted2009-05-21
Permission granted2009-08-03
2 months after submission
Operational2011-02-24
19 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Leverton Ings
Solar Photovoltaics · Operational
126.5 km
Low Farm Solar Farm
Solar Photovoltaics · Under Construction
49.97.4 km
Staples Anaerobic Digestion CHP Plant (Waste AD)
Anaerobic Digestion · Operational
1.48.4 km
Lincoln Farm
Solar Photovoltaics · Operational
11.412.5 km
Bicker Fen (previously Manor Farm)
Solar Photovoltaics · Operational
22.612.9 km
The Hollies
Wind Onshore · Operational
2.613.4 km
Boston Landfill Scheme
Landfill Gas · Operational
1.313.6 km
Boston Landfill, Wyberton - Solar PV Array
Solar Photovoltaics · Under Construction
9.713.7 km

How big is Marsh Farm (Farm AD)?

Marsh Farm (Farm AD) has a recorded installed capacity of 1.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Marsh Farm (Farm AD)?

REPD records the operator as Staples Brothers. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Marsh Farm (Farm AD) approved and built?

The application was submitted on 2009-05-21. Permission was granted on 2009-08-03, 2 months later. The site became operational on 2011-02-24, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 222.