Novarly ParcelRenewable sites

Renewable sitesBicker Fen (previously Manor Farm)

Bicker Fen (previously Manor Farm)

Bicker Fen (previously Manor Farm) is an operational 22.6 MW solar farm in East Lindsey, generating since 12 March 2024. Planning permission was granted on 30 November 2017, 7 months after submission. Operator of record: Innova Renewables Limited.

22.6 MW
Capacity
as recorded in REPD
Operational
Status
since 12 March 2024
Solar Photovoltaics
Technology
Innova Renewables Limited
East Lindsey
Authority
England

Planning and build timeline

Application submitted2 May 2017
Permission granted30 November 2017
7 months after submission
Operational12 March 2024
75 months after consent

Screening a site of your own?

RedlineUK · £39

East Lindsey approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bicker Fen (previously Manor Farm)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Lindsey’s record on solar

East Lindsey has decided 28 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in East Lindsey

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
11.40.9 km
Solar Photovoltaics · Operational
8.62.9 km
Wind Onshore · Operational
2.63.3 km
Solar Photovoltaics · Under Construction
49.95.5 km
Solar Photovoltaics · Operational
4.97.1 km
Anaerobic Digestion · Operational
1.412.9 km
Solar Photovoltaics · Operational
514.9 km

How big is Bicker Fen (previously Manor Farm)?

Bicker Fen (previously Manor Farm) has a recorded installed capacity of 22.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bicker Fen (previously Manor Farm)?

REPD records the operator as Innova Renewables Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bicker Fen (previously Manor Farm) approved and built?

The application was submitted on 2 May 2017. Permission was granted on 30 November 2017, 7 months later. The site became operational on 12 March 2024, 75 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1694.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode