Renewable sites › The Hollies
The Hollies
The Hollies is an operational 2.6 MW onshore wind farm in East Lindsey, generating since 1 January 2008. Planning permission was granted on 29 October 2004, 28 months after submission. Operator of record: National Wind Power.
Planning and build timeline
| Application submitted | 2 July 2002 |
| Permission granted | 29 October 2004 28 months after submission |
| Operational | 1 January 2008 38 months after consent |
Screening a site of your own?
East Lindsey approves 50% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with The Hollies’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Lindsey’s record on onshore wind
East Lindsey has decided 14 onshore wind schemes and approved 50%, taking a median of 15.9 months. See every onshore wind scheme decision in East Lindsey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 8.6 | 0.7 km |
Solar Photovoltaics · Operational | 11.4 | 2.6 km |
Solar Photovoltaics · Operational | 22.6 | 3.3 km |
Solar Photovoltaics · Operational | 4.9 | 3.9 km |
Solar Photovoltaics · Under Construction | 49.9 | 6.4 km |
Anaerobic Digestion · Operational | 1.4 | 13.4 km |
Wind Offshore · Operational | 97.2 | 14.1 km |
Wind Offshore · Operational | 97.2 | 14.6 km |
How big is The Hollies?
The Hollies has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates The Hollies?
REPD records the operator as National Wind Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was The Hollies approved and built?
The application was submitted on 2 July 2002. Permission was granted on 29 October 2004, 28 months later. The site became operational on 1 January 2008, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3186.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode