Renewable sites › Low Farm Solar Farm
Low Farm Solar Farm
Low Farm Solar Farm is under construction in East Lindsey with a recorded capacity of 49.9 MW.
Planning and build timeline
| Application submitted | 2020-12-22 |
| Permission granted | 2021-03-29 3 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Lindsey’s record on solar
East Lindsey has decided 28 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in East Lindsey →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lincoln Farm Solar Photovoltaics · Operational | 11.4 | 5.1 km |
Bicker Fen (previously Manor Farm) Solar Photovoltaics · Operational | 22.6 | 5.5 km |
The Hollies Wind Onshore · Operational | 2.6 | 6.4 km |
THE HOLLIES SOLAR PARK - SKEGNESS Solar Photovoltaics · Operational | 8.6 | 6.5 km |
Marsh Farm (Farm AD) Anaerobic Digestion · Operational | 1.4 | 7.4 km |
Skegness Solar Park Solar Photovoltaics · Operational | 4.9 | 10 km |
Leverton Ings Solar Photovoltaics · Operational | 12 | 11.8 km |
Staples Anaerobic Digestion CHP Plant (Waste AD) Anaerobic Digestion · Operational | 1.4 | 12.3 km |
How big is Low Farm Solar Farm?
Low Farm Solar Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Low Farm Solar Farm?
REPD records the operator as Gresham House / Anesco Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Low Farm Solar Farm approved and built?
The application was submitted on 2020-12-22. Permission was granted on 2021-03-29, 3 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8053.