Renewable sites › Boston Landfill, Wyberton - Solar PV Array
Boston Landfill, Wyberton - Solar PV Array
Boston Landfill, Wyberton - Solar PV Array is under construction in Boston with a recorded capacity of 9.7 MW.
Planning and build timeline
| Application submitted | 2021-06-11 |
| Permission granted | 2022-01-21 7 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Boston’s record on solar
Boston has decided 14 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in Boston →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Boston Landfill Scheme Landfill Gas · Operational | 1.3 | 0.5 km |
Riverside Industrial Estate Gasification Plant Advanced Conversion Technologies · Operational | 10.5 | 0.9 km |
Marsh Lane - Solar PV Panels Solar Photovoltaics · Under Construction | 0.89 | 1.4 km |
Pinguin Foods Solar Photovoltaics · Operational | 1.5 | 1.7 km |
Fen Road Solar Photovoltaics · Operational | 1.4 | 5 km |
Kirton Solar PV Farm Solar Photovoltaics · Operational | 3.2 | 7 km |
Canopus Farm Solar Photovoltaics · Operational | 5 | 7.1 km |
Nowhere Farm Solar Photovoltaics · Operational | 8.1 | 7.8 km |
How big is Boston Landfill, Wyberton - Solar PV Array?
Boston Landfill, Wyberton - Solar PV Array has a recorded installed capacity of 9.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Boston Landfill, Wyberton - Solar PV Array?
REPD records the operator as Infinis Solar Developments Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Boston Landfill, Wyberton - Solar PV Array approved and built?
The application was submitted on 2021-06-11. Permission was granted on 2022-01-21, 7 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9193.
Novarly Parcel · official public data, read properly · parcel.novarly.com