Renewable sites › Oakdale Business Park
Oakdale Business Park
Oakdale Business Park is operational in Caerphilly with a recorded capacity of 4 MW, and has been generating since 2013-12-24.
Planning and build timeline
| Application submitted | 2011-07-18 |
| Permission granted | 2011-10-06 3 months after submission |
| Operational | 2013-12-24 27 months after consent |
Caerphilly’s record on onshore wind
Caerphilly has decided 6 onshore wind schemes and approved 50%, taking a median of 3.2 months. See every onshore wind scheme decision in Caerphilly →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land at Darran Farm Solar Photovoltaics · Operational | 2.6 | 0.6 km |
Manmoel Road Solar Park Solar Photovoltaics · Operational | 4.1 | 1.9 km |
Upper Pant-Ysgawen Farm/Crumlin Solar Photovoltaics · Operational | 4.9 | 2.1 km |
Hafod-Y-Dafal Farm Solar Photovoltaics · Operational | 14 | 4.4 km |
Cwmcaesingrug Farm Solar Photovoltaics · Operational | 10 | 5.8 km |
Penrhiwarwydd Farm Solar Photovoltaics · Operational | 8.5 | 6.1 km |
Gelliargwellt Uchaf Farm AD Anaerobic Digestion · Operational | 1.4 | 7.2 km |
Hendai Farm Solar Photovoltaics · Operational | 13.4 | 7.4 km |
How big is Oakdale Business Park?
Oakdale Business Park has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Oakdale Business Park?
REPD records the operator as Resonance. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Oakdale Business Park approved and built?
The application was submitted on 2011-07-18. Permission was granted on 2011-10-06, 3 months later. The site became operational on 2013-12-24, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3726.