Novarly ParcelRenewable sites

Renewable sitesOakdale Business Park

Oakdale Business Park

Oakdale Business Park is an operational 4 MW onshore wind farm in Caerphilly, generating since 24 December 2013. Planning permission was granted on 6 October 2011, 3 months after submission. Operator of record: Resonance.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 24 December 2013
Wind Onshore
Technology
Resonance
Caerphilly
Authority
Wales

Planning and build timeline

Application submitted18 July 2011
Permission granted6 October 2011
3 months after submission
Operational24 December 2013
27 months after consent

Screening a site of your own?

RedlineUK · £39

Caerphilly approves 50% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Oakdale Business Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Caerphilly’s record on onshore wind

Caerphilly has decided 6 onshore wind schemes and approved 50%, taking a median of 3.2 months. See every onshore wind scheme decision in Caerphilly

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.60.6 km
Solar Photovoltaics · Operational
4.11.9 km
Solar Photovoltaics · Operational
4.92.1 km
Solar Photovoltaics · Operational
144.4 km
Solar Photovoltaics · Operational
105.8 km
Solar Photovoltaics · Operational
8.56.1 km
Anaerobic Digestion · Operational
1.47.2 km
Solar Photovoltaics · Operational
13.47.4 km

How big is Oakdale Business Park?

Oakdale Business Park has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Oakdale Business Park?

REPD records the operator as Resonance. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Oakdale Business Park approved and built?

The application was submitted on 18 July 2011. Permission was granted on 6 October 2011, 3 months later. The site became operational on 24 December 2013, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3726.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode