Mamhilad Solar Farm
Mamhilad Solar Farm is operational in Torfaen with a recorded capacity of 5 MW, and has been generating since 2020-02-12.
Planning and build timeline
| Application submitted | 2015-08-24 |
| Permission granted | 2015-12-22 4 months after submission |
| Operational | 2020-02-12 50 months after consent |
Torfaen’s record on solar
Torfaen has decided 5 solar farms and approved 100%, taking a median of 3.4 months. See every solar farm decision in Torfaen →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land at Lower House Farm Solar Photovoltaics · Operational | 8.1 | 4.1 km |
Llancayo Solar Farm Solar Photovoltaics · Operational | 3.9 | 5.4 km |
Clytha Road - Biomass Boiler Unit Biomass (dedicated) · Operational | 0.99 | 5.7 km |
Penpergwm Solar Farm (Great House Farm) Solar Photovoltaics · Under Construction | 32 | 9.5 km |
Land to North West of Lodge Farm (Park Farm) Solar Photovoltaics · Operational | 4 | 10.3 km |
Hafod-Y-Dafal Farm Solar Photovoltaics · Operational | 14 | 11.5 km |
Cwrt Henllys Farm Solar Photovoltaics · Operational | 5 | 11.8 km |
Upper Pant-Ysgawen Farm/Crumlin Solar Photovoltaics · Operational | 4.9 | 11.9 km |
How big is Mamhilad Solar Farm?
Mamhilad Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mamhilad Solar Farm?
REPD records the operator as Active Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mamhilad Solar Farm approved and built?
The application was submitted on 2015-08-24. Permission was granted on 2015-12-22, 4 months later. The site became operational on 2020-02-12, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5683.