Land at Lower House Farm is operational in Monmouthshire with a recorded capacity of 8.1 MW, and has been generating since 2016-03-21.

8.1 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-21
Solar Photovoltaics
Technology
3C Energy
Monmouthshire
Authority
Wales

Planning and build timeline

Application submitted2012-08-08
Permission granted2012-12-10
4 months after submission
Operational2016-03-21
39 months after consent

Monmouthshire’s record on solar

Monmouthshire has decided 10 solar farms and approved 100%, taking a median of 4.4 months. See every solar farm decision in Monmouthshire

Other built sites within 15 km

SiteMWDistance
Clytha Road - Biomass Boiler Unit
Biomass (dedicated) · Operational
0.991.8 km
Llancayo Solar Farm
Solar Photovoltaics · Operational
3.92.4 km
Mamhilad Solar Farm
Solar Photovoltaics · Operational
54.1 km
Penpergwm Solar Farm (Great House Farm)
Solar Photovoltaics · Under Construction
327.3 km
Manor Farm (Monmouthshire)
Solar Photovoltaics · Operational
10.511.3 km
Land to North West of Lodge Farm (Park Farm)
Solar Photovoltaics · Operational
413.1 km
Hafod-Y-Dafal Farm
Solar Photovoltaics · Operational
1414.7 km

How big is Land at Lower House Farm?

Land at Lower House Farm has a recorded installed capacity of 8.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land at Lower House Farm?

REPD records the operator as 3C Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land at Lower House Farm approved and built?

The application was submitted on 2012-08-08. Permission was granted on 2012-12-10, 4 months later. The site became operational on 2016-03-21, 39 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5006.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council