Renewable sitesLonglands Lane

Longlands Lane

Longlands Lane is operational in Neath Port Talbot with a recorded capacity of 1.5 MW, and has been generating since 2014-12-01.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-12-01
Wind Onshore
Technology
Renewable Energy Systems (RES)
Neath Port Talbot
Authority
Wales

Planning and build timeline

Application submitted2012-10-30
Permission granted2013-11-06
12 months after submission
Operational2014-12-01
13 months after consent

Neath Port Talbot’s record on onshore wind

Neath Port Talbot has decided 20 onshore wind schemes and approved 70%, taking a median of 24.6 months. See every onshore wind scheme decision in Neath Port Talbot

Other built sites within 15 km

SiteMWDistance
Margam Green Energy Plant
Biomass (dedicated) · Operational
400 km
Western Wood Energy Plant
Biomass (dedicated) · Operational
141.1 km
Mynydd Brombil Wind Farm
Wind Onshore · Operational
82.2 km
Pant-Y-Moch Farm
Solar Photovoltaics · Operational
54.2 km
Caergarw Farm
Solar Photovoltaics · Operational
3.84.2 km
Pioneer 2 - Hydrogen Production Facility
Hydrogen · Under Construction
2.57.1 km
Baglan Bay Solar Farm - Phase 1
Solar Photovoltaics · Operational
57.6 km
Stormy Down Solar Farm
Solar Photovoltaics · Operational
3.87.8 km

How big is Longlands Lane?

Longlands Lane has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Longlands Lane?

REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Longlands Lane approved and built?

The application was submitted on 2012-10-30. Permission was granted on 2013-11-06, 12 months later. The site became operational on 2014-12-01, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4196.