Renewable sites › Margam Green Energy Plant
Margam Green Energy Plant
Margam Green Energy Plant is an operational 40 MW biomass plant in Neath Port Talbot, generating since 1 December 2017. Planning permission was granted on 8 March 2011, 28 months after submission. Operator of record: Glennmont Partners.
Planning and build timeline
| Application submitted | 13 November 2008 |
| Permission granted | 8 March 2011 28 months after submission |
| Operational | 1 December 2017 81 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Neath Port Talbot: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Margam Green Energy Plant’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 1.5 | 0 km |
Biomass (dedicated) · Operational | 14 | 1.1 km |
Wind Onshore · Operational | 8 | 2.2 km |
Solar Photovoltaics · Operational | 5 | 4.2 km |
Solar Photovoltaics · Operational | 3.8 | 4.2 km |
Hydrogen · Under Construction | 2.5 | 7.1 km |
Solar Photovoltaics · Operational | 5 | 7.6 km |
Solar Photovoltaics · Operational | 3.8 | 7.8 km |
How big is Margam Green Energy Plant?
Margam Green Energy Plant has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Margam Green Energy Plant?
REPD records the operator as Glennmont Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Margam Green Energy Plant approved and built?
The application was submitted on 13 November 2008. Permission was granted on 8 March 2011, 28 months later. The site became operational on 1 December 2017, 81 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 113.