Renewable sitesStormy Down Solar Farm

Stormy Down Solar Farm

Stormy Down Solar Farm is operational in Bridgend with a recorded capacity of 3.8 MW, and has been generating since 2017-03-27.

3.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-27
Solar Photovoltaics
Technology
Belisama Energy
Bridgend
Authority
Wales

Planning and build timeline

Application submitted2015-05-13
Permission granted2015-08-27
3 months after submission
Operational2017-03-27
19 months after consent

Bridgend’s record on solar

Bridgend has decided 6 solar farms and approved 100%, taking a median of 3.5 months. See every solar farm decision in Bridgend

Other built sites within 15 km

SiteMWDistance
Parc Stormy, Stormy Down
Wind Onshore · Operational
2.50.5 km
Stormy Down (Waste AD)
Anaerobic Digestion · Operational
30.5 km
Newton Down
Wind Onshore · Operational
51.1 km
Tythegston Landfill Site
Landfill Gas · Operational
1.22 km
Seaview Farm
Solar Photovoltaics · Operational
1.72.5 km
Caergarw Farm
Solar Photovoltaics · Operational
3.83.7 km
Court Colman solar park
Solar Photovoltaics · Operational
153.8 km
Longlands Lane
Wind Onshore · Operational
1.57.8 km

How big is Stormy Down Solar Farm?

Stormy Down Solar Farm has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stormy Down Solar Farm?

REPD records the operator as Belisama Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stormy Down Solar Farm approved and built?

The application was submitted on 2015-05-13. Permission was granted on 2015-08-27, 3 months later. The site became operational on 2017-03-27, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6520.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council