Long Mountain is an operational 27.6 MW onshore wind farm in Causeway Coast and Glens, generating since 15 December 2016. Planning permission was granted on 5 January 2007, 10 months after submission. Operator of record: Energia Renewables.
Planning and build timeline
| Application submitted | 8 March 2006 |
| Permission granted | 5 January 2007 10 months after submission |
| Operational | 15 December 2016 119 months after consent |
Screening a site of your own?
Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Long Mountain’s recorded coordinate — swap in your own postcode or coordinates.
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 25 | 1.6 km |
Wind Onshore · Operational | 2.3 | 3.5 km |
Wind Onshore · Operational | 6.9 | 3.5 km |
Solar Photovoltaics · Operational | 5.9 | 4 km |
Solar Photovoltaics · Operational | 18 | 5.4 km |
Wind Onshore · Operational | 15 | 8.1 km |
Wind Onshore · Operational | 25 | 10.7 km |
Wind Onshore · Operational | 5 | 11.9 km |
How big is Long Mountain?
Long Mountain has a recorded installed capacity of 27.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Long Mountain?
REPD records the operator as Energia Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Long Mountain approved and built?
The application was submitted on 8 March 2006. Permission was granted on 5 January 2007, 10 months later. The site became operational on 15 December 2016, 119 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4652.