Glenbuck

Glenbuck is operational in Causeway Coast and Glens with a recorded capacity of 6.9 MW, and has been generating since 2017-03-01.

6.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-03-01
Wind Onshore
Technology
Energia Renewables
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted2006-11-01
Permission granted2011-06-27
56 months after submission
Operational2017-03-01
68 months after consent

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Glenbuck
Wind Onshore · Operational
2.30 km
Bann Road (Tullaghans Road)
Solar Photovoltaics · Operational
252.2 km
Long Mountain
Wind Onshore · Operational
27.63.5 km
Finvoy Road
Solar Photovoltaics · Operational
5.97.3 km
Gruig Wind Farm
Wind Onshore · Operational
258.2 km
Bann Road (Rasharkin)
Solar Photovoltaics · Operational
188.7 km
Corkey Wind Farm
Wind Onshore · Operational
58.8 km
Corkey Wind Farm Extension
Wind Onshore · Operational
2.59.3 km

How big is Glenbuck?

Glenbuck has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glenbuck?

REPD records the operator as Energia Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glenbuck approved and built?

The application was submitted on 2006-11-01. Permission was granted on 2011-06-27, 56 months later. The site became operational on 2017-03-01, 68 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3962.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council