Onshore wind planning in Causeway Coast and Glens
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97% of them, taking a median of 27.4 months to decide. Consented capacity: 521 MW. 13 applications still awaiting a decision.
How Causeway Coast and Glens compares
Against the 75 UK authorities with 5+ onshore wind decisions, Causeway Coast and Glens sits in the 95th percentile for approval rate (29 points above the England average) and the 8th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (60)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wind Turbine Development in Ballymoney Drumabest Farm Limited · LA01/2025/0125/F | 0.25 | Application Withdrawn | 2025-12-18 |
Dungiven Renewable Energy Systems (RES) · LA01/2019/0922/F · 71.9 mo to decide | 24 | Awaiting Construction | 2025-07-31 |
Ballindreen Road - Wind Turbine Solo Power · LA01/2024/0938/F · 10.3 mo to decide | 0.5 | Awaiting Construction | 2025-06-23 |
Moyarget Road - Wind Turbine Greystone Renewables Limited · LA01/2025/0192/F | — | Application Submitted | 2025-03-05 |
Turbine Development in Garvagh Currie Engineering (Garvagh) Ltd · LA01/2025/0052/F | — | Application Submitted | 2025-01-08 |
Dunbeg South Wind Farm - Extension Renewable Energy Systems (RES) · LA01/2024/1221/F | 16.8 | Application Submitted | 2024-11-01 |
Shinny Road, Macosquin - Wind Turbine North Power Croaghan · LA01/2023/1022/F | — | Application Submitted | 2023-10-04 |
62 Muldonagh Road, Claudy - Wind Turbine Unknown · LA11/2023/1754/F | 8.8 | Application Submitted | 2023-06-19 |
Brishey Wind Farm ABO Wind · LA01/2023/0008/F | 28.8 | Application Submitted | 2023-01-05 |
Terrydoo Road 1 Arena Capital Partners · LA01/2020/0483/F · 31.9 mo to decide | 0.3 | Awaiting Construction | 2022-11-17 |
Terrydoo Road 2 Arena Capital Partners · LA01/2020/0433/F · 32.2 mo to decide | 0.3 | Awaiting Construction | 2022-11-17 |
Rigged Hill Wind Farm (Repowering) Scottish Power Renewables · LA01/2019/0890/F · 37.7 mo to decide | 28 | Awaiting Construction | 2022-10-05 |
Power Generation Development in Claudy Tree Top Farms · LA11/2022/0873/F | 0.3 | Application Submitted | 2022-09-15 |
Stroan Road Private Developer · LA01/2020/0451/F · 25.8 mo to decide | 0.3 | Awaiting Construction | 2022-06-29 |
Moyarget Road Cape Renewables · LA01/2020/0585/F · 21.6 mo to decide | 0.3 | Awaiting Construction | 2022-04-06 |
Curragh Road Private Developer · LA01/2020/0895/F · 19 mo to decide | 0.3 | Awaiting Construction | 2022-03-29 |
Corkey Windfarm (repowering) ScottishPower Renewables · LA01/2019/0772/F · 31.8 mo to decide | 20 | Awaiting Construction | 2022-03-02 |
Drumack Lane Replacement Turbine Arena Capital Partners Limited · LA01/2021/0205/F · 12 mo to decide | — | Awaiting Construction | 2022-02-23 |
Mullan Road BSI Wind · LA01/2020/0321/F · 15.6 mo to decide | 0.3 | Awaiting Construction | 2021-06-30 |
Ballyavelin Road Replacement Turbine Private Developer · LA01/2021/0240/F | — | Application Submitted | 2021-02-26 |
Dunbeg South Wind Farm Renewable Energy Systems (RES) · LA01/2018/0200/F · 33.9 mo to decide | 29.7 | Awaiting Construction | 2020-12-17 |
Moyarget Road HHT Renewables Limited · LA01/2020/1213/F | 0.25 | Application Submitted | 2020-11-16 |
Windyhill Road Private Developer · LA01/2019/1153/F · 12.8 mo to decide | 0.2 | Awaiting Construction | 2020-11-12 |
Dullaghy Road Private Developer · LA01/2019/0268/F | 0.3 | Application Withdrawn | 2020-02-10 |
Reservoir Road Private Developer · LA01/2020/0078/F | 0.2 | Application Submitted | 2020-01-21 |
Greenhall Highway (resubmission/variation) Private Developer · LA01/2019/0751/F | 0.3 | Revised | 2019-07-02 |
Islandranny Road J and J Energies · LA01/2018/1267/F · 6.2 mo to decide | 0.3 | Awaiting Construction | 2019-06-18 |
Evishagaran Wind Farm ERG UK Holding · LA01/2018/1151/F · 6.7 mo to decide | 46.8 | Awaiting Construction | 2019-04-17 |
Croaghan North Power Croaghan Ltd · C/2011/0158/F | 12.5 | Application Withdrawn | 2018-08-22 |
Dunmore Wind Farm - extension TCI Renewables · B/2013/0241/F · 54.6 mo to decide | 24 | Awaiting Construction | 2018-06-15 |
Carneatly North Power Ltd · E/2011/0088/F | 9.2 | Application Withdrawn | 2018-06-07 |
Armoy Wind Farm ABO Wind NI · LA01/2017/1654/F | 19.8 | Appeal Refused | 2017-12-22 |
Dunbeg Extension Gaelectric · LA01/2016/0061/F · 16.2 mo to decide | 9 | Awaiting Construction | 2017-04-27 |
Cam Burn Wind Farm TCI Renewables · C/2011/0459/F · 63.5 mo to decide | 13.8 | Abandoned | 2016-12-22 |
Evishagaran Wind Farm ERG Renew · B/2013/0120/F · 33.9 mo to decide | 35 | Revised | 2016-04-04 |
Brockaghboy Wind Farm - extension Greencoat · H/2014/0241/F · 16.1 mo to decide | 10 | Operational | 2015-10-27 |
Craiggore windfarm Renewable Energy Systems (RES) · B/2012/0268/F · 28.6 mo to decide | 23.5 | Operational | 2015-03-05 |
Altaveedan Wind Farm NTR PLC · D/2010/0356/F · 34.8 mo to decide | 17.9 | Operational | 2013-10-28 |
Windy Hill ARC NI 1 / Windy Fields · C/2013/0248/F | 52.5 | Appeal Withdrawn | 2013-07-01 |
Upper Ballyrogan Wind Farm TCI Renewables · C/2012/0276/F · 9 mo to decide | 11.5 | Abandoned | 2013-04-11 |
Cloonty Wind Farm Gaelectric Developments/ CGN Europe Energy · D/2009/0142/F · 45.6 mo to decide | 12 | Operational | 2013-03-27 |
Smulgedon Gaelectric Developments · B/2009/0070/F · 43.4 mo to decide | 16.1 | Abandoned | 2012-10-02 |
Corkey Wind Farm Extension Northern Ireland Renewables · D/2010/0060/F · 23.7 mo to decide | 2.5 | Operational | 2012-02-10 |
Brockaghboy Wind Farm Greencoat · C/2007/1186/F · 49.1 mo to decide | 37.5 | Operational | 2012-01-18 |
Glenbuck Energia Renewables · D/2006/0599/F · 55.8 mo to decide | 6.9 | Operational | 2011-06-27 |
Windyhill Road (Dunbeg) Wind Farm Gaelectric Developments/ CGN Europe Energy · B/2007/0560/FUL · 37.5 mo to decide | 42 | Operational | 2011-01-27 |
Farkland Ted Walsh & Associates� · B/2007/0562/F | 51 | Application Withdrawn | 2010-11-11 |
Dunmore TCI Renewables · 34.6 mo to decide | 21 | Operational | 2010-10-29 |
Lisnamuck Wind Farm Lisnamuck Wind Farm Limited · C/2008/0163/F | 6 | Application Withdrawn | 2010-10-01 |
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2) Scottish and Southern Energy (SSE) · B/2007/0006/F · 44.5 mo to decide | 27.6 | Operational | 2010-09-26 |
Corkey Wind Farm Extension Northern Ireland Renewables · D/2008/0404/F | 2.3 | Revised | 2010-07-29 |
Slieve Kirk (formerly Glenconway) Scottish and Southern Energy (SSE) · B/2006/0607/F · 26.1 mo to decide | 18.4 | Operational | 2009-02-17 |
Gruig Wind Farm Foresight Group · D/2004/0790/F · 32.2 mo to decide | 25 | Operational | 2007-06-25 |
Glenbuck Energia Renewables · D/2005/0628/F · 22.5 mo to decide | 2.3 | Operational | 2007-04-22 |
Long Mountain Energia Renewables · D/2006/0104/F · 10 mo to decide | 27.6 | Operational | 2007-01-05 |
Garves Mountain Farm Gravis Capital Management · D/2003/0329/F · 41.3 mo to decide | 15 | Operational | 2006-11-20 |
Altahullion Phase II B9 Energy / RES · B/2004/0795/F · 16.4 mo to decide | 11.7 | Operational | 2006-04-06 |
Altahullion Renewable Energy Systems (RES) / BP Energy · 4 mo to decide | 26 | Operational | 2001-10-01 |
Rigged Hill Wind Farm B9 Energy Services Ltd/ ScottishPower Renewables · 7.4 mo to decide | 5 | Operational | 1994-07-01 |
Corkey Wind Farm B9 Energy Services Ltd/ ScottishPower Renewables · 7.2 mo to decide | 5 | Operational | 1994-06-29 |
Does Causeway Coast and Glens approve onshore wind schemes?
Yes — of the 37 onshore wind schemes Causeway Coast and Glens has decided, 97% were approved (36 granted, 1 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Causeway Coast and Glens?
The median time from application to decision is 27.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Causeway Coast and Glens consented?
521 MW has been consented across 36 approved schemes, with 20 MW refused. A further 13 applications awaits a decision.
Other technologies in Causeway Coast and Glens
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.