Onshore wind planning in Causeway Coast and Glens

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97% of them, taking a median of 27.4 months to decide. Consented capacity: 521 MW. 13 applications still awaiting a decision.

97%
Approved
36 granted · 1 refused
27.4 mo
Median decision
UK 11.5 mo
521 MW
Consented
20 MW refused
7
Appeals
5 allowed on appeal

How Causeway Coast and Glens compares

Against the 75 UK authorities with 5+ onshore wind decisions, Causeway Coast and Glens sits in the 95th percentile for approval rate (29 points above the England average) and the 8th percentile for speed.

Decisions by year

510Approved — 2 (2010)210Approved — 2 (2011)211Approved — 2 (2012)212Approved — 2 (2013)213Approved — 2 (2015)215Approved — 1 (2017)117Approved — 1 (2018)118Approved — 2 (2019)219Approved — 2 (2020)220Approved — 1 (2021)121Approved — 8 (2022)822Approved — 2 (2025)225
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (60)

SchemeMWStatusDecided
Wind Turbine Development in Ballymoney
Drumabest Farm Limited · LA01/2025/0125/F
0.25Application Withdrawn2025-12-18
Dungiven
Renewable Energy Systems (RES) · LA01/2019/0922/F · 71.9 mo to decide
24Awaiting Construction2025-07-31
Ballindreen Road - Wind Turbine
Solo Power · LA01/2024/0938/F · 10.3 mo to decide
0.5Awaiting Construction2025-06-23
Moyarget Road - Wind Turbine
Greystone Renewables Limited · LA01/2025/0192/F
Application Submitted2025-03-05
Turbine Development in Garvagh
Currie Engineering (Garvagh) Ltd · LA01/2025/0052/F
Application Submitted2025-01-08
Dunbeg South Wind Farm - Extension
Renewable Energy Systems (RES) · LA01/2024/1221/F
16.8Application Submitted2024-11-01
Shinny Road, Macosquin - Wind Turbine
North Power Croaghan · LA01/2023/1022/F
Application Submitted2023-10-04
62 Muldonagh Road, Claudy - Wind Turbine
Unknown · LA11/2023/1754/F
8.8Application Submitted2023-06-19
Brishey Wind Farm
ABO Wind · LA01/2023/0008/F
28.8Application Submitted2023-01-05
Terrydoo Road 1
Arena Capital Partners · LA01/2020/0483/F · 31.9 mo to decide
0.3Awaiting Construction2022-11-17
Terrydoo Road 2
Arena Capital Partners · LA01/2020/0433/F · 32.2 mo to decide
0.3Awaiting Construction2022-11-17
Rigged Hill Wind Farm (Repowering)
Scottish Power Renewables · LA01/2019/0890/F · 37.7 mo to decide
28Awaiting Construction2022-10-05
Power Generation Development in Claudy
Tree Top Farms · LA11/2022/0873/F
0.3Application Submitted2022-09-15
Stroan Road
Private Developer · LA01/2020/0451/F · 25.8 mo to decide
0.3Awaiting Construction2022-06-29
Moyarget Road
Cape Renewables · LA01/2020/0585/F · 21.6 mo to decide
0.3Awaiting Construction2022-04-06
Curragh Road
Private Developer · LA01/2020/0895/F · 19 mo to decide
0.3Awaiting Construction2022-03-29
Corkey Windfarm (repowering)
ScottishPower Renewables · LA01/2019/0772/F · 31.8 mo to decide
20Awaiting Construction2022-03-02
Drumack Lane Replacement Turbine
Arena Capital Partners Limited · LA01/2021/0205/F · 12 mo to decide
Awaiting Construction2022-02-23
Mullan Road
BSI Wind · LA01/2020/0321/F · 15.6 mo to decide
0.3Awaiting Construction2021-06-30
Ballyavelin Road Replacement Turbine
Private Developer · LA01/2021/0240/F
Application Submitted2021-02-26
Dunbeg South Wind Farm
Renewable Energy Systems (RES) · LA01/2018/0200/F · 33.9 mo to decide
29.7Awaiting Construction2020-12-17
Moyarget Road
HHT Renewables Limited · LA01/2020/1213/F
0.25Application Submitted2020-11-16
Windyhill Road
Private Developer · LA01/2019/1153/F · 12.8 mo to decide
0.2Awaiting Construction2020-11-12
Dullaghy Road
Private Developer · LA01/2019/0268/F
0.3Application Withdrawn2020-02-10
Reservoir Road
Private Developer · LA01/2020/0078/F
0.2Application Submitted2020-01-21
Greenhall Highway (resubmission/variation)
Private Developer · LA01/2019/0751/F
0.3Revised2019-07-02
Islandranny Road
J and J Energies · LA01/2018/1267/F · 6.2 mo to decide
0.3Awaiting Construction2019-06-18
Evishagaran Wind Farm
ERG UK Holding · LA01/2018/1151/F · 6.7 mo to decide
46.8Awaiting Construction2019-04-17
Croaghan
North Power Croaghan Ltd · C/2011/0158/F
12.5Application Withdrawn2018-08-22
Dunmore Wind Farm - extension
TCI Renewables · B/2013/0241/F · 54.6 mo to decide
24Awaiting Construction2018-06-15
Carneatly
North Power Ltd · E/2011/0088/F
9.2Application Withdrawn2018-06-07
Armoy Wind Farm
ABO Wind NI · LA01/2017/1654/F
19.8Appeal Refused2017-12-22
Dunbeg Extension
Gaelectric · LA01/2016/0061/F · 16.2 mo to decide
9Awaiting Construction2017-04-27
Cam Burn Wind Farm
TCI Renewables · C/2011/0459/F · 63.5 mo to decide
13.8Abandoned2016-12-22
Evishagaran Wind Farm
ERG Renew · B/2013/0120/F · 33.9 mo to decide
35Revised2016-04-04
Brockaghboy Wind Farm - extension
Greencoat · H/2014/0241/F · 16.1 mo to decide
10Operational2015-10-27
Craiggore windfarm
Renewable Energy Systems (RES) · B/2012/0268/F · 28.6 mo to decide
23.5Operational2015-03-05
Altaveedan Wind Farm
NTR PLC · D/2010/0356/F · 34.8 mo to decide
17.9Operational2013-10-28
Windy Hill
ARC NI 1 / Windy Fields · C/2013/0248/F
52.5Appeal Withdrawn2013-07-01
Upper Ballyrogan Wind Farm
TCI Renewables · C/2012/0276/F · 9 mo to decide
11.5Abandoned2013-04-11
Cloonty Wind Farm
Gaelectric Developments/ CGN Europe Energy · D/2009/0142/F · 45.6 mo to decide
12Operational2013-03-27
Smulgedon
Gaelectric Developments · B/2009/0070/F · 43.4 mo to decide
16.1Abandoned2012-10-02
Corkey Wind Farm Extension
Northern Ireland Renewables · D/2010/0060/F · 23.7 mo to decide
2.5Operational2012-02-10
Brockaghboy Wind Farm
Greencoat · C/2007/1186/F · 49.1 mo to decide
37.5Operational2012-01-18
Glenbuck
Energia Renewables · D/2006/0599/F · 55.8 mo to decide
6.9Operational2011-06-27
Windyhill Road (Dunbeg) Wind Farm
Gaelectric Developments/ CGN Europe Energy · B/2007/0560/FUL · 37.5 mo to decide
42Operational2011-01-27
Farkland
Ted Walsh & Associates� · B/2007/0562/F
51Application Withdrawn2010-11-11
Dunmore
TCI Renewables · 34.6 mo to decide
21Operational2010-10-29
Lisnamuck Wind Farm
Lisnamuck Wind Farm Limited · C/2008/0163/F
6Application Withdrawn2010-10-01
Slieve Kirk (formerly Altahullion Phase III & Glenconway 2)
Scottish and Southern Energy (SSE) · B/2007/0006/F · 44.5 mo to decide
27.6Operational2010-09-26
Corkey Wind Farm Extension
Northern Ireland Renewables · D/2008/0404/F
2.3Revised2010-07-29
Slieve Kirk (formerly Glenconway)
Scottish and Southern Energy (SSE) · B/2006/0607/F · 26.1 mo to decide
18.4Operational2009-02-17
Gruig Wind Farm
Foresight Group · D/2004/0790/F · 32.2 mo to decide
25Operational2007-06-25
Glenbuck
Energia Renewables · D/2005/0628/F · 22.5 mo to decide
2.3Operational2007-04-22
Long Mountain
Energia Renewables · D/2006/0104/F · 10 mo to decide
27.6Operational2007-01-05
Garves Mountain Farm
Gravis Capital Management · D/2003/0329/F · 41.3 mo to decide
15Operational2006-11-20
Altahullion Phase II
B9 Energy / RES · B/2004/0795/F · 16.4 mo to decide
11.7Operational2006-04-06
Altahullion
Renewable Energy Systems (RES) / BP Energy · 4 mo to decide
26Operational2001-10-01
Rigged Hill Wind Farm
B9 Energy Services Ltd/ ScottishPower Renewables · 7.4 mo to decide
5Operational1994-07-01
Corkey Wind Farm
B9 Energy Services Ltd/ ScottishPower Renewables · 7.2 mo to decide
5Operational1994-06-29

Does Causeway Coast and Glens approve onshore wind schemes?

Yes — of the 37 onshore wind schemes Causeway Coast and Glens has decided, 97% were approved (36 granted, 1 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Causeway Coast and Glens?

The median time from application to decision is 27.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Causeway Coast and Glens consented?

521 MW has been consented across 36 approved schemes, with 20 MW refused. A further 13 applications awaits a decision.

Other technologies in Causeway Coast and Glens

Solar in Causeway Coast and GlensBattery storage in Causeway Coast and Glens

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.