Corkey Wind Farm

Corkey Wind Farm is an operational 5 MW onshore wind farm in Causeway Coast and Glens, generating since 1 December 1994. Planning permission was granted on 29 June 1994, 7 months after submission. Operator of record: B9 Energy Services Ltd/ ScottishPower Renewables.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 December 1994
Wind Onshore
Technology
B9 Energy Services Ltd/ ScottishPower Renewables
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted22 November 1993
Permission granted29 June 1994
7 months after submission
Operational1 December 1994
5 months after consent

Screening a site of your own?

RedlineUK · £39

Causeway Coast and Glens approves 97% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Corkey Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Causeway Coast and Glens’s record on onshore wind

Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.50.5 km
Wind Onshore · Operational
252.8 km
Wind Onshore · Operational
17.94.9 km
Wind Onshore · Operational
6.98.8 km
Wind Onshore · Operational
2.38.8 km
Wind Onshore · Operational
1210.8 km
Solar Photovoltaics · Operational
2511 km
Wind Onshore · Operational
27.611.9 km

How big is Corkey Wind Farm?

Corkey Wind Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Corkey Wind Farm?

REPD records the operator as B9 Energy Services Ltd/ ScottishPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Corkey Wind Farm approved and built?

The application was submitted on 22 November 1993. Permission was granted on 29 June 1994, 7 months later. The site became operational on 1 December 1994, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3103.