Finvoy Road

Finvoy Road is an operational 5.9 MW solar farm in Causeway Coast and Glens, generating since 15 December 2017. Planning permission was granted on 10 August 2015, 8 months after submission. Operator of record: Lightsource Renewable Energy.

5.9 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2017
Solar Photovoltaics
Technology
Lightsource Renewable Energy
Causeway Coast and Glens
Authority
Northern Ireland

Planning and build timeline

Application submitted4 December 2014
Permission granted10 August 2015
8 months after submission
Operational15 December 2017
28 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Causeway Coast and Glens: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Finvoy Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
181.5 km
Wind Onshore · Operational
27.64 km
Solar Photovoltaics · Operational
255.1 km
Wind Onshore · Operational
156.3 km
Wind Onshore · Operational
6.97.3 km
Wind Onshore · Operational
2.37.3 km
Wind Onshore · Operational
2514.6 km

How big is Finvoy Road?

Finvoy Road has a recorded installed capacity of 5.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Finvoy Road?

REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Finvoy Road approved and built?

The application was submitted on 4 December 2014. Permission was granted on 10 August 2015, 8 months later. The site became operational on 15 December 2017, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4884.