Renewable sites › Garves Mountain Farm
Garves Mountain Farm
Garves Mountain Farm is operational in Causeway Coast and Glens with a recorded capacity of 15 MW, and has been generating since 2009-01-01.
Planning and build timeline
| Application submitted | 2003-06-11 |
| Permission granted | 2006-11-20 41 months after submission |
| Operational | 2009-01-01 25 months after consent |
Causeway Coast and Glens’s record on onshore wind
Causeway Coast and Glens has decided 37 onshore wind schemes and approved 97%, taking a median of 27.4 months. See every onshore wind scheme decision in Causeway Coast and Glens →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Bann Road (Rasharkin) Solar Photovoltaics · Operational | 18 | 5.7 km |
Finvoy Road Solar Photovoltaics · Operational | 5.9 | 6.3 km |
Bann Road (Tullaghans Road) Solar Photovoltaics · Operational | 25 | 8 km |
Long Mountain Wind Onshore · Operational | 27.6 | 8.1 km |
Glenbuck Wind Onshore · Operational | 2.3 | 9.8 km |
Glenbuck Wind Onshore · Operational | 6.9 | 9.8 km |
Brockaghboy Wind Farm Wind Onshore · Operational | 37.5 | 13 km |
How big is Garves Mountain Farm?
Garves Mountain Farm has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Garves Mountain Farm?
REPD records the operator as Gravis Capital Management. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Garves Mountain Farm approved and built?
The application was submitted on 2003-06-11. Permission was granted on 2006-11-20, 41 months later. The site became operational on 2009-01-01, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3191.
Novarly Parcel · official public data, read properly · parcel.novarly.com