Renewable sitesBarling Hall Farm

Barling Hall Farm

Barling Hall Farm is an operational 2.4 MW landfill gas site in Rochford, generating since 1 June 2004. Planning permission was granted on 4 February 2000, 5 months after submission. Operator of record: Cory Environmental.

2.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1 June 2004
Landfill Gas
Technology
Cory Environmental
Rochford
Authority
England

Planning and build timeline

Application submitted25 August 1999
Permission granted4 February 2000
5 months after submission
Operational1 June 2004
52 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Rochford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barling Hall Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
56.3 km
Solar Photovoltaics · Operational
2.56.9 km
Solar Photovoltaics · Operational
58 km
Solar Photovoltaics · Under Construction
49.998.9 km
Battery · Under Construction
208.9 km
Wind Onshore · Operational
17.59.5 km
Wind Onshore · Operational
20.711.5 km
Solar Photovoltaics · Under Construction
3013.5 km

How big is Barling Hall Farm?

Barling Hall Farm has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barling Hall Farm?

REPD records the operator as Cory Environmental. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barling Hall Farm approved and built?

The application was submitted on 25 August 1999. Permission was granted on 4 February 2000, 5 months later. The site became operational on 1 June 2004, 52 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 735.